Bethel Road Water Loop-CN 2020-07-09 ♦ e c • c 1 r r
o r
COPPELL
• ' s e4
Change Order No. 2
Date of Issuance: July 2,2020 Effective Date:July 2,2020
Owner: City of Coppell Owner's Contract No.: WA 18-01
Contractor: 9 Oaks Realty LLC
Engineer: Alan Plummer Associates Inc
Project: Bethel Road Water Loop
The Contract is modified as follows upon execution of this Change Order:
Description: . 1)Addition of 43 LF of the 30 inch bore to eliminate damage to the large tree on the West end of
the project, Labor and Materials in the amount of$22,403.00.Addition of 7 contract days. 2) Extra work on the
North side of Bethel due to the actual location of the 8" water line differing from the plans,extra work on the
West end of the project for abandoning the 16"water line,fittings,excavation, and restoration Labor and
Materials in the amount of$14,640.00.Addition of 14 contract days 3)Addition of 22 contract days due to
rain. 5)Addition of 21 contract days due to Frontier conflict.
Attachments: Price quote
CHANGE IN CONTRACT PRICE CHANGE IN CONTRACT TIMES
[note changes in Milestones if applicable]
Original Contract Price: Original Contract Times: 120 Days
$288,000.00
Total from previously approved Change Order No. 1 Total from previously approved Change Order No. 1
Days: 0
$24,900.00
Contract Price prior to this Change Order: Contract Times prior to this Change Order:
Days: 120
$312,900.00
[Increase]of this Change Order: [Increase]of this Change Order:
Days: 64
$ 37,043.00
Contract Price incorporating this Change Order: Contract Time "r h all approved Change Orders:
Da s: 184
$ 349,943.00
RECOM ENDED: • CE' ED: Alir ACCEPTED:
By. ,. By: _ By:
City Engineer Owner Authoriz:d Signature) Contractor Authorized Signature
Title: Kent Collins Title Mike Land Title: Ram Sunkavli
Date: 7,0-.201 Z® Date Jvtl,1,q p Date
EJCDC'C-941,Change Order.
Prepared and published 2013 by the Engineers Joint Contract Documents Committee.
Page 1 of 2
TE.Hinter. Estimate
Tejas Utilities LLC #EST-022
POBOX 338
COPPELL Texas 75019
214-989-6566
ram@tejasutilities.com
WWW.PIPEBORE.COM
Estimate Date: 07Jun 2020
Project Name: W.Bethel Rd Water loop
Bill To
City of Coppell
# Item& Description Qty Rate Amount
1 30- Inch Bore 43.00 521.00 22,403.00
Additional Bore under Trees LF
2 8" MJ 45 BEND 1.00 240.00 240.00
North of Bethel
3 8" MJ PVC RESTRAINT 4.00 100.00 400.00
North of Bethel
4 Excavation and Back fill 4.00 2,500.00 10,000.00
North and West of Bethel Rd DAY
5 Landscaping and Irrigation 100.00 10.00 1,000.00
North of Bethel SF
6 Cap 16"T 1.00 1,500.00 1,500.00
West Bethel Rd EA
7 Cut and Plug 16"Water line 1.00 1,500.00 1,500.00
West Bethel Rd EA
Sub Total 37,043.00
Total $37,043.00
Notes
Looking forward for your business.