Rebcon IncCity of Coppell Public Works Department Routing Sheet for Approval of Contracts and Agreements Vendor Name: Rebcon Inc, Date: 9/28/2021 Contracted Work /Project: Denton Tap Intersection Improvements Prolect - CO#1 Explanation: CO for the construction of an 8 -ft bike path from Heartz Rd to Denton Tap Rd- $169,755.50 0✓ 0✓ Council Approved. Yes / No If yes, Date:9/28/2021 Budget Approved: Yes / No Ethics Certificate Required: Yes / No If Yes, Copy is Attached: Yes / No ® New Vendor FLA ®Existing Vendor ® Renewing Contract Routing Sequence: Initials Date 1. Employee initiating contract/agreement: mike garza mg_ 9/28/2c (Include W-9 & CIQ form if vendor is not in system.) 2. Supervisor Authorization: 3. Purchasing Manager/Technician: (Signature needed only if vendor is new to system or contract has been changed since last time used) 4. Director of Public Works Authorization, Kent Collins /Cr' 5. Deputy City Manager Authorization Comments: 6. City Manager: Comments: Traci Leach/Vicki Chiavetta � /O �il,�/ Mike Land 7. Originals back to Administrative Manager: Kyra Jansen _ 8. Copy of contract/agreement to Jennifer Miller. DYES / NO= Y o COPPELL NX Date of Issuance: Sept. 28, 2021 Owner: City of Coppell Contractor: Rebcon Inc, Engineer: Kimley-Horn Project. Denton Tap Intersection Improvements Change Order No. Effective Date: Sept. 28, 2021 Owner's Contract No.: ST 19-01 The Contract is modified as follows upon execution ofthis Change Order: This change order is to add an 8' hike and bike trail along Parkway Blvd from Heartz rd, to Denton Tap, Total CO #1$169,755.50 and an addition of 30 days. CHANGE IN CONTRACT PRICE RECOMMENDED: CHANGE IN CONTRACTTIMES ('note changes in Milestones if applicable] Original Contract Price: Original Contract Time: $2,7779148.70 390 days Total from previously approved Change Orders No. N/A Total from previously approved Change Orders No. to No. N/A N/A to No. N/A Days: 30 $0 Contract Price prior to this Change Order: Contract Times prior to this Change Order: Days: 390 $2,777,148.70 • [Increase] of this Change Order: [Increase] of this Change Order: Days: 30 $169,755.50 Contract Price incorporating this Change Order: Contract Times with all approved Change Orders: ys: 4dn $ 2j946,90410 PTE ACC PT By' By' By' ~ CltyofCoppell Directorof Public Works City of Coppel City Manager Rebcon Inc, Title: Kent Collins, P.E. l0 • y L � Date: Title Mike Land Title: Date Date Jim Schumann fo i zap ! EJCDC C-941, Change Order. Prepared and published 2013 by the Engineers Joint Contrail Documents Committee. Page i of 2 Denton •Tap Road Intersection'Improvements Project No. ST -19-01 Coppell, Texas Amendment #1 - Trail Extension Date: 9/2/2021 Construction Cost: Item No. Item Descrl tion Quanti Unit Unit Price Item Cost 10 - D RIGHT OF WAY PREPARATION 10 STA $2,800.00 $28,000.00 11 - D UNCLASSIFIED EXCAVATION 155 CY $45.00 $6,975.00 12 - D REMOVE EXISTING CONCRETE PAVEMENT (TO INCLUDE CURBS/PAVERS 20 SY $30.00 $600.00 13 - D REMOVE EXISTING CONCRETE SIDEWALK &RAMPS 535 SY $15.00 $8,025.00 20 - D 8" REINFORCED CONCRETE STREET PAVEMENT 25 SY $95.00 $2,375.00 22 - D 8" LIME STABILIZED SUBGRADE 90 SY $12.00 $1,080.00 23 - D LIME FOR STABILIZED SUBGRADE 40 LB/SY 1 TON $180.00 $180.00 24 - D 8" STAMPED COLORED CONC PVMT CROSSWALK 65 SY $220.00 $14,300.00 25 - D 6" STAMPED COLORED CONC PVMT MEDIAN 15 SY $235.00 $3 525.00 25A - D 6" REINFORCED CONCRETE MEDIAN 10 SY $100.00 $1,000.00 26 - D 4" REINFORCED CONCRETE SIDEWALK ALL WIDTHS -40 SY $52.00 -$2,080.00 26A - D 6" THICK CONCRETE TRAIL 3800 PSI 905 SY $70.00 $63,350.00 27 - D CONC RETAINING WALL W/ INTEGRAL SIDEWALK (CAST- IN-PLACE -250 SF $275.00 -$68,750.00 27A - D CONC RETAINING WALL WI INTEGRAL SIDEWALK (CAST- IN-PLACE 8' WIDTH 330 SF $300.00 $99,000.00 28 - D BARRIER FREE PEDESTRIAN RAMP 7 SY $247.00 $1,729.00 40 - D STREET SIGNS 3 EA $520.00 $1,560.00 50 - D REMOVE EXISTING FIRE HYDRANT 1 EA $500.00 $500.00 51 - D ADJUST EXISTING WATER VALVE 4 EA $275.00 $1,100.00 66 - D CONDT PVC SCH 40 3" TRENCH SIGNAL -25 LF $16.50 -$412.50 70 - D ELEC CONDR N0.6 BARE SIGNAL -25 LF $2.20 -$55.00 91 - D TRF SIG CBL TY A 14 AWG 10 CONDR -215 LF $4.40 -$946.00 99 - D PED POLE ASSEMBLY -1 EA $3,300.00 -$3,300.00 112 - D RESTORE PARKWAYS &DISTURBED AREAS 10 STA $1,200.00 $12,000.00 Notes: Total: $169,755.50 1. Please add thirty (30) calendar days to the Protect for this work. 2. Rebcon is In agreement with Kimley-Horn's probable cost for Item 25A - D. 3. Rebcon disagrees with Kimley-Horn's probable cost for Item 27A - D, but it Is close enough to accept. 4. Rebcon disagrees with Kimley-Horns probable cost for Item 26A - D and will accept an Item Unit Price of $70.00/SY. The additional 2" thickness of concrete and the increased PSI strength of the concrete warrant the additional $5.00/SY in the Unit Price.