WA9402-CS 911206 Aco,s &
8333 DouSlas Avenue, ~820 Dallas, T~xas
ROSS L. JACOBS, RE.
I.C. FINKLEA, RE. December 6, 1991
JAMES E. LAUGHLIN,
RONALD V. CONWAY, RE.
JOHN W. BIRKHOFF, P.E,
MATT ARMSTRONG, P.E.
JOE R. CARTER, RE.
GARY C. HENDRICKS, P.E.
C. L. SHIMEK,
Mr. Steven L. Bacchus Mr. Howard L. Pafford
City of Lewtsville City of Coppell
1197 W. Main Street Post Office Box 478
Lewisville, Texas 75067 Coppell, Texas 75019
Mr. Steve Gilbreath
2121 Cross Timbers Road
Flower Mound, Texas 75028
Gentlemen:
You have previously been furnished estimated costs for participating in the
construction of a water supply line with the City of Irving, as follows:
Capacity ..... MGD Estimated Cost
Total 95 $ 4,636,000
Irving 65 3,172,000
Flower Mound 10 488,000
Coppell 10 488,000
Lewisville 10 488,000
Some interest has been expressed in the cost of additional capacity above the
assumed amounts used in the above calculations. Following is a tabulation of
estimated costs for large amounts:
Capacity, MGD Estimated Cost
Total 115 $ 5,050,000
Irving 65 2,855,000
Flower Mound 20 878,000
Coppell 20 878,000
Lewisville 10 439,000
These costs are based on 'S~aled distances and approximate prevailing prices at the
present time. Any variation in actual capacity contracted will, of course, change
the allocation of costs accordingly.
Sincerely,
C. L. Shimek, P.E.
cc: Mr. Ron McCuller