ST0702-MP090320 87892 8~ILRoad South sttl.Jc:ture Improvements Ken Griffin, P.E. Caleb Thornhill, P.E.; FNI Project Manager Keith Marvin (Coppell); Trish Hatley (FNI), Aaron Litteken (FNI), File - - ~ .., Project Updates: · Contacted by DART 3-20-09. They asked why the Drainage Report was not signed and sealed. We told them once plans were finalized, reports, plans, etc..would be signed and sealed and sent to DART. · ROW document revised and included in this status report. · Memo sent regarding street lighting providing possible options. Submittal/Meeting · 100% Plans and Specs Submittal DATE TBD - pending street lighting configuration Additional Information: · Once DART gives approval of communication line, and licensure procedures, complete package will be sent to DART including Application, checklist, drainage report, applicable plans, licensure fees and signed statement from City's Stormwater Manager approving plans. · Schedule meeting to discuss street lighting and ROW for Bethel next week.