(8/18/2009) Keith Marvin - RE: Coppell RoadPage 1
From: Keith Marvin
To:Roberts, Ken
Date: 10/26/2007 12:52 PM
Subject: RE: Coppell Road
Thanks for the update.
Feel free to call with any questions.
Keith
Keith Marvin, P.E.
Project Engineer
(972) 304-3681
>>> "Roberts, Ken" <kar@Huitt-Zollars.com> 10/26/2007 12:23 PM >>>
Keith,
We are just getting back into the Coppell Road project due to some large
projects that we have just finished up. I am planning on making a
submittal to you on November 30. I am sure as we get into the plans we
will have some questions that need to be answered. I will stay in
contact with you. If you need anything in the interim, let me know.
Kenneth Roberts, PE
Huitt-Zollars, Inc.
-----Original Message-----
From: Keith Marvin [mailto:kmarvin@ci.coppell.tx.us]
Sent: Thursday, October 25, 2007 10:35 AM
To: Roberts, Ken
Cc: Ken Griffin
Subject: Coppell Road
Ken,
I want to touch base with you on the progress of Coppell Road. Since we
met in July we have acquired right of way or easement from 3 of the 6
affected property owners, and we are in dialog with the remaining
owners. We hope to be successful in our negotiations, however if we are
not we may need to discuss some modifications to the ADA ramps. The
affected intersections are Cooper and Kaye Street.
We hosted a utility coordination meeting on August 14, 2007. At that
meeting we discussed our expectation for the utilities to be clear by
the first quarter of 2008. We have subsequently had meetings and dialog
with Oncor(TXU) and Verizon.
The expectation of the city is that we complete the design of this
project, bid the project, and begin construction no later than the
second quarter of 2008.
Please let me know if you have any questions about this schedule, or to
discuss any intermediate dates for review, bidding, council approval,
etc...
(8/18/2009) Keith Marvin - RE: Coppell RoadPage 2
Keith Marvin, P.E.
Project Engineer
(972) 304-3681