ST0003-CS080228(8/1812009) Keith Marvin -Fwd: Copell Road - ST 00-03
From: Leslie Henderson
To: kar~huitt-zollars.com; Keith Marvin
Date: 2/28/2008 4:05 PM
Subject: Fwd: Copell Road - ST 00-03
Attachments: Copell Road - ST 00-03
FYI-
Attached is a question I received for the Coppell Rd. project to go into the addendum.
Thanks,
Leslie Henderson
Purchasing Technician
City of Coppell
255 Parkway Blvd.
Coppell, TX 75019
Page 1
Page 1 of 1
Keith Marvin -Copell Road - ST 00-03
m~ _. ~a z
From: "Rick Howard" <RHoward~a,Austin-Ind.com>
To: <lenderson@ci.coppelLtx.us>
Date: 2/28/2008 4:00 PM
Subject: Copell Road - ST 00-03
Ms. Henderson
This project calls out the 3~d Edition of the COG Spec. Item 5.8.2 of this spec with regards to Contraction Joints
requires that we sawcut within a 5 to 12 hour window unless it is listed on the plans. To meet this spec, we would
have to stop our paving by 1:00 PM so that we are not sawing concrete after 6:00 PM. If we paved past 1:00 PM
we could not saw within the 12 hour limit.
This requirement changed in the 4th Edition
Could you get a clarification?
Thanks
Rick Howard
Austin Bridge & Road
Direct: 214 596-7345