ST0003-CS080626Page 1 of 2
Keith Marvin - Re: Coppell Road Move 6/19/08 meeting summary
From: <richard.ll .trevino@verizon.com>
To: <tammie.dean@verizon.com>
Date: 6/26/20081:28 PM
Subject: Re: Coppell Road Move 6/19/08 meeting summary
CC: <danny.fortune@verizon.com>, <stephens.clifford@verizon.com>,
<darin.e.box@verizon.com>, <jenny.j.ruppert@verizon.com>,
<mat307@SBCglobal.net>, <michael.brown@verizon.com>,
<olen.cl.steele@verizon.com>, <stefani.wilkinson@verizon.com>,
<tammie.dean@verizon.com>, <carl.x.shipman@verizon.com>,
<keith.e.jones(cwerizon.com>, <rodell@ci.coppell.tx.us>, <kmarvin(c~ci.coppell.tx.us>
Attachments: Coppell Road Move MEETING #1 SUMMARY 6-19-08.doc
Tammie,
We will be needing to set up a face to face meeting with Engineering (ASAP) to discuss dates and the
necessary changes that need to be made out in the field and to the narratives to these two work orders. I have
given my large set of prints to Mid America so that we can continue to work until the Gadded prints are received.
There is also a section of Aerial cable on the far South side that needs to be moved by the end of next week so
that we are out of the way of the new water line that is being installed, which will involve pulling of poles,
transferring cables and placing new IPIDs to allow cables to be moved back 12ft of the new poles. these pages
are not on the set prints that are presently in the field.
It would also be in the best interest of all involved parties to attend Thursday Meetings @ 9:OOAM to discuss
and answerthe City of Coppells questions to upcoming and unforeseen changes aswe progress. Regards
Thanks,
Richard Trevino
Coordinator
FTTP OSP Construction Lewisville
972-318-3247 office
214-437-6452 cellular
Tammie M. Dean1EMPLITXNerizon Richard L. TrevinolEMPLITXIVerizon@VZNotes, Cliff E.
StephenslEMPLITXIVerizon@VZNotes, Charles D.
Fortune/EMPLlTXIVerizon@VZNotes, Olen C.
06/20/2008 02:24 PM SteelelVENDITXIVerizon@VZNotes, Darin E.
To Box/EMPLlTXIVerizon@VZNotes, Michael W.
BrownIEMPLITXIVerizon@VZNotes, Stefani R.
WilkinsonlEMPL1TX1Verizon@VZNotes, Jenny J.
RuppertlEMPLITXIVerizon@VZNotes, Tammie M.
DeanIEMPLITXIVerizon@VZNotes, mat307@SBCglobal.net
cc
Subject Coppell Road Move 6/19/08 meeting summary
file://C:1Documents and SettingslradloolLocal SettingslTemplXPgrpwise148639971 City_o... 8/18/2009
Page 2 of 2
Attached below is the Coppell Road Move meeting summary from the conference call that was held on Thursday
June 19th.
The next meeting is scheduled for:
Date: Thursday July 10, 2007
Time: 2:00 p.m
Conference Bridge: (866) 766-3409 passcode: 5457470#
If you have any questions or updates prior to the next call please feel free to contact me at 972-318-3505.
Thanks,
Tammie Dean
Project Specialist- Project Management
Texas NE&P
Office :9721318-3505
Fax :9721318-1150
tammie.dean@verizon.com
file://C:1Documents and SettingslradloolLocal SettingslTemplXPgrpwise148639971 City_o... 8/18/2009
Coppell Road Move 6/20/2008
VERIZON PROJECT MANAGEMENT MEETING SUMMARY
T0: Attendees
PROJECT: Coppell Road Move ,Coppell TX
PROJECT ISD: September 15, 2008
MEETING DATE: Thursday June 19, 2008 -Meeting # 1
PROJECT DESCRIPTION:
5647.005-3POAOPK
PROVIDE LABOR AND MATERIAL TO REPLACE ALL THE AERIAL CABLE
ALONG COPPELL ROAD. THREE 4" CONDUITS ARE TO BE PLACED ALONG THE
WEST R.O.W. WITH A 1200 PAIR CABLE AND A 600 PAIR CABLE IN TWO DUCTS.
A VACANT CONDUIT IS BEING PLACED FOR FUTURE GROWTH ALONG BETHEL ROAD
AT THE SOUTH END OF THE PROJECT. ALL POLES AND AERIAL CABLES ARE TO
BE REMOVED. WHEN: IN SERVICE JUNE 15, 2008 WHERE: COPPELL
ROAD FROM SANDY LAKE ROAD SOUTH TO COPPELL STREET. WHY: COPPELL
ROAD IS BEING WIDENED. STORM DRAIN AND NEW WATER LINES ARE BEING
PLACED. REVISION 2 (5/8/2008)ISSUED TO CHANGE ROUTING OF COPPER
CABLE PER CITY OF COPPELL. COPPER CABLE IS BEING CHANGED FROM
UNDERGROUND TO BURIED.
5647-005-3PFAOHY
PROVIDE LABOR AND MATERIAL TO REPLACE SEVERAL SECTIONS OF FIBER
OPTIC CABLE ALONG COPPELL ROAD. COPPELL ROAD IS BEING CUT DOWN AND A
NEW STORM DRAIN AND WATER LINE IS BEING PLACED. FIBER CABLE NEEDS TO
BE LOWERED SO CITY LINES CAN BE PLACED. WHEN: IN-SERVICE JUNE 15,
2008. WHERE: COPPELL ROAD FROM SANDY LAKE ROAD SOUTH TO COOPER
STREET. WHY: COPPELL ROAD IS BEING WIDENED. STORM DRAIN AND NEW
WATER LINES ARE BEING PLACED.
PURPOSE OF MEETING:
The purpose of this meeting was to discuss the major milestones, and identify any issues that will affect the
successful completion of these projects.
NEXT MEETING:
MEETING DATE: Thursday, July 10, 2008
MEETING TIME: 2:OOPM CDT
ACCESS #: 866-766-3409 passcode 5457470#
If you have any questions regarding this meeting or project, please contact me at (972) 318-3505
Tammie Dean
Project Manager
1
Coppell Road Move 6/20/2008
ATTENDEE LIST
The following individual with an (X) before their names were in attendance at this meeting. Please ensure that
each of the attendees receive a copy of this meeting summary.
Coppell Road Move TEAM ATTENDEE LIST:
Name Department
X CliffStephens Network Eng/Ping-Texas
Danny Fortune Construction -Texas
Y Darin Box Network Eng/Ping-Texas
X Jenny Ruppert Network Eng/Ping- Texas
Olan Steele Network Eng/Ping- Texas
a Mike Richard
Mike Brown Network Eng/Ping- Texas
Y Rick Trevino Network Ops West -Texas
Stefani Wilkinson NetworkEng/Ping-Texas
X Tammie Dean Network Eng/Ping -Texas
PROJECT WORK ORDERS
Coppell Road Move Work Orders
Phone # Role Email Address
972-318-1554 Network Engineer stephens.clifford@verizon.coi
972-318-5132 Mgr-Construction danny.fortune@.verizon.com
972-318-5184 SEC MGR-NETWORK ENGINEERING Dazin.box@verizon.com
325-944-6034 SPEC-NETWORK ENGINEERING Jenny Ruppet@verizon.com
972-318-5284 Olan.steele@verizon.com
817-577-2772 Mid-America Mat307rSBC~loobal.net
972-578-3354 OSP Network Engineering michael.brown@verizon.com
972-318-3247 Coord Network Ops- Construction richazd.l l.trevino@.verizon.a
903-885-1742 SPEC-NETWORK ENGINEERING stefani.wilkinson@verizon.co
972-318-3505 Project Specialist tammie.dean@verizon.com
Work Order ACTIVITY I
TASK CMS Schell
Detail En 'r CMS Actual
Detail Eng'r CMS WO
Approval CMS Schell
Mat. Ship CMS Actual
Mat. Ship CMS Schell
Const. Start CMS Actual
Const. Start CMS Schell
In-Serv CMS Actual
In-Sere
5647-005- Aerial 03-11-OS 03-11-08 03-12-OS 03-12-08 06-20-OS 10-15-08
3POAOPK Copper
Re lacment
5647-005- Fiber 03-11-OS 03-11-08 03-12-08 06-05-08 06-05-OS 06-20-08 09-15-08 i
3PFOHY re lacement
I. PREVIOUS ACTION ITEMS
None
II. CURRENT BUSINESS ITEMS
1.01 Permits - Olan Steele /Rick Trevino -Closed
All City of Coppell permits where picked upon Thursday June 19tH
2
Coppell Road Move 6/20/2008
1.02 Material Status -Jenny Reppert /Rick Trevino -Open
WO 3PFOHY all material on hand to start job
WO 3POAOPK - 600 pr on hand, will be using 1200 pr from IF work order, Email sent to AI Dill to
cancel the 1200 pr cable from this order. Jenny to order 900, 300 & 400 pr cable needed.
VZ to provide all class 2 material, Mid-America to supply remaining class 1 material.
1.03 Daily Reporting -Mike Richard /Jenny Repper - On-Going
Since Mid-America does not have access to V-Build yet, they will be reporting the placing statis
Jenny via email at ~nny.repper(cr)verizon.com. Jenny to follow up with in need to get Mid-
America access to V-Build.
1,04 Job Prints - Olan Steele -Open
Olan to meet with Rick and Mid-America on Friday 6/20 at 10am to delivery a new set of job
prints. Olan to mark a new pole setting on Mid-America current prints.
1.05 Work start / Completions -Mid America
Mid America has called in locates for all work orders. They are scheduled to to start on next
week and are schedule to complete all placing by the end of August.
III. OPEN DISCUSSION
1.06 Weekly Meetings- Ricky -Mid America - On-Going
Will attend weekly meetings on Thursday mornings at 9AM with Road Move construction
company trailer which is located near Bass Pro shop.
IV. PENDING ACTION ITEMS
1.02 Material Updates Jenny Reppert /Rick Trevino -Open
1.03 Daily Reporting -Mike Richard /Jenny Repper - On-Going
1.04 Job Prints - Olan Steele -Open
1.05 Bi-Weekly Updates -Rick Trenvo /Mike Richard - MidAmerica