ST0003-CS080916
Page 1 of 3
Keith Marvin - Re: Coppell Road Project
From: <stephens.clifford@verizon.com>
To: "Keith Marvin" <kmarvin@ci.coppell.tx.us>
Date: 9/16/2008 7:39 AM
Subject: Re: Coppell Road Project
Mr. Marvin all splicing was completed on Coppell Rd. 9/16/08 late. We are contacting Mid-America to wreck out
cable 9/17/08.
CLIFF STEPHENS
LOCAL MANAGER CONSTRUCTION
LEWISVILLE, TX
(972)318-1554
"Keith Marvin" <kmarvin@ci.coppell.tx.us>
To
Cliff E. Stephens/EMPL/TX/Verizon@VZNotes
cc
09/15/2008 03:12 PM
SubjectRe: Coppell Road Project
That's great. I though for sure this storm would have had an impact on the schedule.
Keith Marvin, P.E.
Project Engineer
(972) 304-3681
>>> <stephens.clifford@verizon.com> 9/15/2008 1:23 PM >>>
As of 9/15/08 everything is on target for splicing completion by 9/22/08.
If anything changes I will send you an e-mail.
CLIFF STEPHENS
LOCAL MANAGER CONSTRUCTION
LEWISVILLE, TX
(972)318-1554
"Keith Marvin" <kmarvin@ci.coppell.tx.us>
09/15/2008 01:13 PM
To
Cliff E. Stephens/EMPL/TX/Verizon@VZNotes
file://C:\Documents and Settings\radloo\Local Settings\Temp\XPgrpwise\48CF6294City_o...8/18/2009
Page 2 of 3
cc
"Robert Caudill" <rcaudill@TiseoPaving.com>, Charles D.
Fortune/EMPL/TX/Verizon@VZNotes, Kelly K. Baumann/EMPL/TX/Verizon@VZNotes,
Richard L. Trevino/EMPL/TX/Verizon@VZNotes, Steve M.
Olinsky/EMPL/TX/Verizon@VZNotes
Subject
Re: Coppell Road Project
Cliff,
I'm guessing that most of your manpower is being sent elsewhere to work on
storm damage. Any idea how this may impact the completion of this
project?
Keith
Keith Marvin, P.E.
Project Engineer
(972) 304-3681
>>> <stephens.clifford@verizon.com> 9/12/2008 7:17 AM >>>
The splicing on the Coppell rd. move is at 90% completion as of 9/12/08.
We are still on target to complete splicing by 9/22/08.
CLIFF STEPHENS
LOCAL MANAGER CONSTRUCTION
LEWISVILLE, TX
(972)318-1554
"Keith Marvin" <kmarvin@ci.coppell.tx.us>
09/11/2008 04:40 PM
To
Charles D. Fortune/EMPL/TX/Verizon@VZNotes, Cliff E.
Stephens/EMPL/TX/Verizon@VZNotes
cc
"Robert Caudill" <rcaudill@TiseoPaving.com>, Kelly K.
Baumann/EMPL/TX/Verizon@VZNotes, Richard L.
Trevino/EMPL/TX/Verizon@VZNotes, Steve M. Olinsky/EMPL/TX/Verizon@VZNotes
Subject
Coppell Road Project
Gentlemen,
We met this morning as we have been doing for the past several weeks to
discuss the status of utility relocations on the Coppell Road project. We
appreciate the fact that Kelly was able to represent Verizon and give us
some information on the conflict with the 1800 pair cable at the north end
of the project.
Kelly shared his understanding of where we are in the splicing process.
Unfortunately his knowledge is based on a field visit last week. We would
appreciate it if someone with first hand knowledge of the splicing
activity could attend the meeting next week at 9:00am on Thursday.
file://C:\Documents and Settings\radloo\Local Settings\Temp\XPgrpwise\48CF6294City_o...8/18/2009
Page 3 of 3
Our contractor will begin the excavation on the west side of the roadway
either Friday or Monday depending on the weather. +
Keith Marvin, P.E.
Project Engineer
(972) 304-3681
file://C:\Documents and Settings\radloo\Local Settings\Temp\XPgrpwise\48CF6294City_o...8/18/2009