ST0003-CS080918 (8/18/2009) Keith Marvin - RE: Coppell RoadPage 1 From: Keith Marvin To:Caudill, Robert CC:lsmith@tiseopaving.com; Samaniego, Albert Date: 9/18/2008 4:46 PM Subject: RE: Coppell Road Robert, I have several concerns about the progress of this project. My biggest concern is for the safety of pedestrians and vehicular traffic traveling through the work area. As the excavation is being done on the west side of the road there is a vertical cut right at the edge of the travel lane with no shoring and no barrier to prevent vehicles from driving off into the cut. This operation will also be removing the area pedestrians were routed between Archer and the school crosswalk to the north. There are no alternate locations being prepared to accommodate these pedestrians. I am concerned about the existence of these conditions, and the length of time they may remain. At our Thursday morning meeting Randy was unable to give me any schedule on when the storm drain laterals would begin, or even how long it will take for the excavation, let alone when asphalt would be placed and traffic would be moved over. The city of Coppell is very concerned with the adequacy of supervision on this project. There are several items that are continually pointed out to the superintendent that take weeks to be addressed. Tiseo is obligated under the terms of our contract to provide a superintendent with full authority to act on behalf the contractor. We do not think the current level of staffing between this project and the Bethel Road project is adequate. I would like to meet with you on the site at your earliest opportunity. Please let me know your availability. Keith Keith Marvin, P.E. Project Engineer (972) 304-3681 >>> "Robert Caudill" <rcaudill@TiseoPaving.com> 9/17/2008 5:11 PM >>> Keith; The high grass have been cut. Robert Caudill Vice President Tiseo Paving Company (972) 289-0723 -----Original Message----- From: Keith Marvin [mailto:kmarvin@ci.coppell.tx.us] Sent: Wednesday, September 17, 2008 9:00 AM To: Robert Caudill Cc: Albert Samaniego; Lance Smith Subject: Coppell Road Robert, I have received complaints about tall grass and weeds within the work area of the Coppell Road Project. The are of the complain is along the east side of the road north of the school. (8/18/2009) Keith Marvin - RE: Coppell RoadPage 2 Under the provisions of our contract Tiseo has a responsibility to abate this. I have requested that Randy address this, however nothing has been done. Please have someone get in there with a weed eater and knock this grass down. Thanks. Keith Keith Marvin, P.E. Project Engineer (972) 304-3681