(8/18/2009) Keith Marvin - Re: Coppell Rd.Page 1
From:
Keith Marvin
To:
lsmith@TiseoPaving.com
CC:
rcaudill@TiseoPaving.com, Albert Samaniego
Date:
10/13/2008 4:06 PM
Subject:
Re: Coppell Rd.
Lance,
We will review this and get back with you tomorrow.
The two days in October the school was closed was Friday and today.
Keith
-----Original Message-----
From: "Lance Smith" <lsmith@TiseoPaving.com>
To: Keith Marvin <KMARVIN@ci.coppell.tx.us>
Cc: Robert Caudill <rcaudill@TiseoPaving.com>
Sent: 10/13/2008 3:11:45 PM
Subject: Coppell Rd.
Keith,
I wanted to get together with you to discuss our plans for handling the
intersections on Coppell Rd. Briefly, I'll try to explain our plan. We
have decided that the area is too flat to lime and place HMAC at
sub-grade as previously discussed. We are going to place Flex-base and
HMAC to raise the surface of the temp paving and provide better runoff.
Initially we will place the detour road between intersections to
complete the majority of the detour. When the majority is complete we
will close the intersections on the West side of Coppell Rd. That have
access and detour traffic accordingly. These will be done one or two at
a time and reopened the same day. Major intersections such as Ruby and
Plantation will be done during off peak times.
Northbound traffic and traffic from the East side of Coppell will
continue to use the existing pavement as we are removing and lowering
the intersections on the West side. As we open the intersections on the
West side traffic from the West will begin using the new temporary
detour. We will place ramps from the temporary detour to the existing
pavement where needed in order to remove and replace the next
intersections.
We will remove one half at a time the intersections that only have one
way in and one way out such as Park Lane at the trailer park and Oak
(8/18/2009) Keith Marvin - Re: Coppell Rd.Page 2
Grove on the West side and Cooper and Kaye St. on the East side. The
school entrances will be done on Saturday, or another day that the
school is closed. I know you mentioned a day in October that school
would be out, if we could get that date we may be able to use it.
One by one we will get all traffic down to the temporary detour and
then remove the remaining existing pavement. Please call if you have any
questions or concerns and I will try to answer or meet you to discuss.
Thanks Lance