ST0003-CS080911
(8/19/2009) Keith Marvin - Coppell Road ProjectPage 1
From: Keith Marvin
To:danny.fortune@verizon.com; stephens.clifford@verizon.com
CC:Caudill, Robert; kelly.baumann@verizon.com; richard.l1.trevino@verizon...
Date: 9/11/2008 4:40 PM
Subject: Coppell Road Project
Gentlemen,
We met this morning as we have been doing for the past several weeks to discuss the status of utility relocations on the
Coppell Road project. We appreciate the fact that Kelly was able to represent Verizon and give us some information on the
conflict with the 1800 pair cable at the north end of the project.
Kelly shared his understanding of where we are in the splicing process. Unfortunately his knowledge is based on a field
visit last week. We would appreciate it if someone with first hand knowledge of the splicing activity could attend the
meeting next week at 9:00am on Thursday.
Our contractor will begin the excavation on the west side of the roadway either Friday or Monday depending on the
weather. +
Keith Marvin, P.E.
Project Engineer
(972) 304-3681