ST0003-CS090423
(8/20/2009) Keith Marvin - Re: Coppell RoadPage 1
From:
Keith Marvin
To:
rcaudill@TiseoPaving.com
Date:
4/23/2009 8:32 AM
Subject:
Re: Coppell Road
I know.
-----Original Message-----
From: "Robert Caudill" <rcaudill@TiseoPaving.com>
To: Keith Marvin <KMARVIN@ci.coppell.tx.us>
Sent: 4/23/2009 8:27:08 AM
Subject: RE: Coppell Road
Keith;
Can not do a critical path schedule for the sidewalk wall, because we
where still performing work on other areas.
Robert Caudill
Vice President
Tiseo Paving Company
(972) 289-0723
-----Original Message-----
From: Keith Marvin [mailto:KMARVIN@ci.coppell.tx.us]
Sent: Thursday, April 23, 2009 8:22 AM
To: Robert Caudill
Cc: Lance Smith
Subject: Re: Coppell Road
Well, I guess we will need to see a critical path schedule that shows
the overall project has been delayed before we talk about the 3 weeks.
I'll put 10 days on this change order for the new wall.
Keith
-----Original Message-----
From: "Robert Caudill" <rcaudill@TiseoPaving.com>
To: Keith Marvin <KMARVIN@ci.coppell.tx.us>
Cc: Lance Smith <lsmith@TiseoPaving.com>
Sent: 4/23/2009 8:08:34 AM
Subject: Coppell Road
Keith;
Sorry, I did not get back to you in regards to the added time for the
retaining wall change order. The time for the landscape wall is 11 days,
but we lost 3 weeks on what the city wanted to do on the sidewalk wall.
Robert Caudill
(8/20/2009) Keith Marvin - Re: Coppell RoadPage 2
Vice President
Tiseo Paving Company
(972) 289-0723