ST9905-CS071126
(8/21/2009) Keith Marvin - RE: Bethel Rd.Page 1
From:
"Lance Smith" <lsmith@TiseoPaving.com>
To:
"Keith Marvin" <kmarvin@ci.coppell.tx.us>
Date:
11/26/2007 1:25 PM
Subject:
RE: Bethel Rd.
Thanks Keith
-----Original Message-----
From: Keith Marvin [mailto:kmarvin@ci.coppell.tx.us]
Sent: Monday, November 26, 2007 11:39 AM
To: Lance Smith
Subject: Re: Bethel Rd.
Lance,
We're running some copies of the drawings now. Rick tells me the water
line is complete.
Keith
Keith Marvin, P.E.
Project Engineer
(972) 304-3681
>>> "Lance Smith" <lsmith@TiseoPaving.com> 11/21/2007 4:50 PM >>>
Keith,
Please provide Thomas with 6 additional copies of the revised plan
sheets for Creekview Dr. and the modifications to the turn lanes on
Bethel Rd. Also, please let me know when the waterline on Creekview will
be complete and we will schedule accordingly. Have a Happy Thanksgiving!
Lance