ST9905-CS081003 (8/22/2011) Keith Marvin - Re: Bethel Road - Additional Wall footagePage 1 From: Keith Marvin To:Caudill, Robert CC:Odell, Richard; Smith, Lance Date: 10/3/2008 11:02 AM Subject: Re: Bethel Road - Additional Wall footage Robert, When we worked out this change order we established a unit price and an approximate contract quantity. The idea was that the contractor would then work with Rick on the exact limits in the field during construction. I do not see this as an additional 60 square feet of wall. I see this as adjusting the limits of the wall in the field. We do not expect to exceed the quantity established in the change order. We are available to meet out there to discuss this as needed. Keith Marvin, P.E. Project Engineer (972) 304-3681 >>> "Robert Caudill" <rcaudill@TiseoPaving.com> 10/3/2008 9:48 AM >>> Keith; Rick O'Dell has added 60 face feet of wall at the N.E. corner of Bethel and Freeport. Is this correct? Robert Caudill Vice President Tiseo Paving Company (972) 289-0723