ST0702-CS080403
BETHEL & COPPELL
ROAD RECONSTRUCTION
90% Review Coppell Road South
Thursday, April 3, 2008
AGENDA
LIST OF ATTENDEES
Freese and Nichols, Inc.: City of Coppell:
Tricia Hatley, P.E. (THH) Keith Marvin, P.E.
B. Caleb Thornhill, P.E. (BCT) Ken Griffin, P.E.
TECHNICAL10:00 am
1.90% Review
a.Driveways Updated
b.DART Response
c.Construction Timeline – 10 months, 8 months aggressive
d.Project Sign Details
e.Cost Estimate
2.Miscellaneous
a.Sidewalk 5.5 feet?
b.Stamped Crosswalk - $105/sy
i)Burns, Service Entrance, East Development (4 drives), Southwestern, parkway?
c.Relocate Barbwire Fence on East side
d.Include Coppell City Standards in Plans
e.Barrier Free Ramps – ADA Update, PED05
f.Tie to C&P
3.Bethel Rd, Part 1
a.Bridge
b.Other
CLOSE/ADJOURN 12:00 pm