ST0702-MP090629(8/25/2009) Keith Marvin -One-page Report 6-29-09.pdf ~ ~ Page 1
CPL07342
Coppell Road South
Infrastructure Improvements
Keith Marvin, P.E.
Caleb Thornhill, P.E.; FNI Project Manager
Ken Griffin (Coppell}; Trish Hatley (FNI), Aaron Litteken (FNI}, John Manning (FNI}, File
• I will bring the sheets Oncor commented on, full & half size, to the pre-con meeting to be
inserted in the plans. I've also attached an illustration of the proposed pole being used.
Please verify this is the pole the City is requesting.
• Below is a breakdown of the storm drain outfall quantity changes.
Adjusted Percentage
Items Bid Qty Qt difference difference
Unclassified Street
Excavation 10,747 SY 16,007 SY $42,080 +49%
6x4 Box Culvert 501 LF 835 LF $90,514 +67%
8' Concrete V-Lined
Channel 700 SY 380 SY ($12,500 -46%
• Frances Wilson with DART has said {June 26, 2009} our permit looks to be approved, but
she has not received the formal paperwork. I hope she will be at the Pre-Con meeting
Tuesday June 30, 2009.
• 6 full & 6 half size "Issue for Construction" to Pre-Con Meeting.
• City to verify Light Pole from attached exhibit.
SubmiHal/Meeting DATE
• Begin Construction TBD
,. ,; ,.,.
Page 1 of 1