ST0701-CS080410Page 1 of 1 Keith Marvin -Southwestern Bridge Cost Comparison From: "Smith, Madonna" <msmith@Halff.com> To: "Keith Marvin" <KMARVIN@ci.coppell.tx.us>, "Ken Griffin" <kgriffin(a,ci. coppell.tx.us> Date: 4/10/2008 3:01 PM Subject: Southwestern Bridge Cost Comparison CC: "Littleton, Dave" <dlittleton(c~halff.com> Attachments: ESTIMATE.XLS KeithlKen, Our approximated costs for the two bridge options are on the attached excel file. These unit costs are based on average bids from recent projects and the assumption that shale extends 50' below the roadway. I added the 15% contingency to cover items such as grading, riprap, lighting, pavement marking, etc. Let me know if you have questions or comments. Thank you, Madonna Madonna Smith, P.E. ~= Pro ect Mana er ~~~ J g ~~ HALFF ASSOCIATES, INC. 1201 N. Bowser Road Richardson, Texas 75081 Phone 214-217-6688 Fax 214-739-0095 www.halff.com file://C:1Documents and SettingslradloolLocal SettingslTemplXPgrpwise147FE2BB6City_... 8/26/2009 (8/2612009) Keith Marvin - ESTIMATE.XLS Southwestern Blvd (Option 1) Page ITEM N0. DESC CODE S.P. N0. DESCRIPTION UNIT ESTIMATED QUANTITY PRIC PER U 416 2003 RILL SHAFT 30 IN LF 900 $ 420 2003 L C CONC ABUT CY 50.0 $ 420 2004 L C CONC BENT CY 35.0 $ 420 2033 L S CONC APPR SLAB CY 100.0 $ 420 2034 L S CONC SDWLK CY 30.0 $ 422 2001 EINF CONC SLAB SF 7 950 425 2002 RESTR CONC BEAM TY B LF 1 200.0 428 2001 ONC SURF TREAT CLASS 1 SY 750 450 2006 AIL T411 /C411 LF 380.0 $ 454 2001 EALED EXPANSION JOINT 4 IN SEJ-A LF 106 ubTOTAL OTAL 15% Contingency New Total NOTE: This statement was prepared utilizing standard cost andlor quantity estimate practices. It is understood and agreed that this is a statement of probable construction cost only, and the Engineer shall not be liable to the Owneror to any Third Party for any failure to accurately estimate the cost andlor quantities for the project, or any part thereof. Unit prices are in current dollars and should be adjusted as required when letting schedule for project is determined. Date of this printout: <date> Halff Associates, Inc. Confidential <time> (8/2612009) Keith Marvin - ESTIMATE.XLS ~~~ Southwestern Blvd (Option 3) Page 2 ITEM N0. DESC CODE S.P. N0. DESCRIPTION UNIT ESTIMATED QUANTITY PRICE PER UNIT 416 2002 RILL SHAFT 24 IN LF 900 $123. 420 2003 L C CONC ABUT CY 50.0 $735. 420 2004 L C CONC BENT CY 35.0 $703. 420 2033 L S CONC APPR SLAB CY 100.0 $335. 420 2034 L S CONC SDWLK CY 30.0 $375. 422 2001 EINF CONC SLAB SF 7 950 $9. 425 2017 RESTR CONC BEAM 15"Slab Beam LF 1 650.0 $131. 428 2001 ONC SURF TREAT CLASS 1 SY 750 $1. 450 2006 AIL T411/C411 LF 380.0 $106. 454 2001 EALED EXPANSION JOINT 4 IN SEJ-A LF 106 $99. ubTOTAL OTAL 15% Contingency New Total NOTE: This statement was prepared utilizing standard cost andlor quantity estimate practices. It is understood and agreed that this is a statement of probable construction cost only, and the Engineer shall not be liable to the Owneror to any Third Party for any failure to accurately estimate the cost andlor quantities for the project, or any part thereof. Unit prices are in current dollars and should be adjusted as required when letting schedule for project is determined. Date of this printout: <date> Halff Associates, Inc. Confidential <time>