Keith Marvin -Southwestern Boulevard
From: "Littleton, Dave" <dlittleton@halff.com>
To: "Keith Marvin" <kmarvin@ci.coppell.tx.us>,
Oyen" <MattO@PacTrust.com>
Date: 8/20/200810:16 AM
Subject: Southwestern Boulevard
CC: "Rodriguez, Jorge" <jrodriguez@halff.com>
"Ben Chessar" <BenC@PacTrust.com>, "Matt
Gentlemen, I thought of a couple of items to mention regarding the project. First, I spoke with our bridge
designers and they indicate that a 6-month time frame would be recommended for bridge demolition and re-
construction. This is longer than the 4 to 5 months previously indicated. I think that we should work with the
contractors to confirm a reasonable time. Second, we have not shown any street lighting on the project. Let me
know if we need to add street lighting.
B. David Littleton, P.E. ~=
Vice President ~~~
^~
HALFF ASSOCIATES, INC.
1201 N. Bowser Road
Richardson, Texas 75081
Phone 214-346-6200
Fax 214-739-0095
www.halff.com
file://C:1Documents and SettingslradloolLocal SettingslTemplXPgrpwise148ABEEF9City_... 8/26/2009