ST0701-CS090707(8/2812009) Keith Marvin - RE: Southwestern Blvd. Improvements Addendum No. 3
From: "Matt Oyen" <MattO@PacTrust.com>
To: "Keith Marvin" <kmarvin@ci.coppell.tx.us>, "Dave Littleton" <dlittleton@...
CC: "Ben Chessar" <BenC@PacTrust.com>
Date: 717/200910:37 AM
Subject: RE: Southwestern Blvd. Improvements Addendum No. 3
Keith - I don't know if you have already heard back from Jorge, but the
bids were very tight and we have a few questions we need to run through
on the proposals to assure that they have covered all of the items.
However in round numbers the City's section came in under 1.45 million
on all of the proposals. We will try to run through all of our
questions with the contractors in the next couple of days and get the
bid tabulations over to you for your review of the recommended
contractor.
Thanks,
Matt
-----Original Message-----
From: Keith Marvin [mailto:kmarvin@ci.coppell.tx.us]
Sent: Monday, July 06, 2009 9:38 AM
To: Dave Littleton; jrodriguez@halff.com
Cc: Matt Oyen
Subject: Re: Southwestern Blvd. Improvements Addendum No. 3
Jorge,
How did the bids look?
The final piece of fiber to the school has been removed from the poles
on the south side of the road. I have contacted Oncor to have the poles
removed.
Keith
Keith Marvin, P.E.
Project Engineer
(972) 304-3681
»> "Rodriguez, Jorge" <jodriguez@halff.com> 6/301200911:40 AM »>
Gentlemen
Please see the attached Addendum No.3. for Southwestern Blvd.
Improvements
Page 1
Thanks
(8/2812009) Keith Marvin - RE: Southwestern Blvd. Improvements Addendum No. 3
Jorge Rodriguez, P.E.
Project Manager
HALFF ASSOCIATES, INC.
1201 N. Bowser Road
Richardson, Texas 75081
Phone 214-346-6203
Fax 214-739-0095
www. halff.com
Page 2