ST0501-CS080205
(8/15/2011) Keith Marvin - RE: Deforest Road UpdatePage 1
From: Keith Marvin
To:Spann, Quinn
CC:Baskins, DiWanna
Date: 2/5/2008 4:27 PM
Subject: RE: Deforest Road Update
We don't have a set format. We do need to see total contract amount, payments made to date, work completed during
current billing cycle, etc... Probably everything you normally do for other public clients.
If you want to send me an example before you work ours up, we can do that, or you can just send your standard one and
we have any questions we can work it out.
Keith
Keith Marvin, P.E.
Project Engineer
(972) 304-3681
>>> "Quinn Spann" <qspann@gswwengineers.com> 2/5/2008 4:22 PM >>>
I have not sent in a pay request yet. I will be working on that at the
end of the week, I hope. Do you have a set format for invoices? Is so,
can you send me a pdf. If not, I will just do it my normal way.
Quinn G. Spann, Jr., P.E.
Associate / Sr. Project Manager
GSWW, Inc.
11117 Shady Trail
Dallas, Texas 75229
972-620-1255 Ext 225
972-620-8028 Fax
-----Original Message-----
From: Keith Marvin [mailto:kmarvin@ci.coppell.tx.us]
Sent: Tuesday, February 05, 2008 4:09 PM
To: Quinn Spann
Cc: DiWanna Baskins; Dan DeGroot
Subject: Re: Deforest Road Update
Thanks for the update Quinn. We look forward to seeing some preliminary
alignment drawings in a few weeks.
I haven't seen a pay request yet on this project, have I? Please send
them to my attention when they come in.
Keith
Keith Marvin, P.E.
Project Engineer
(972) 304-3681
>>> "Quinn Spann" <qspann@gswwengineers.com> 2/5/2008 4:00 PM >>>
Keith,
(8/15/2011) Keith Marvin - RE: Deforest Road UpdatePage 2
The surveyor provided the survey to us on January 31st. The
Geotechnical has completed the borings. They are now waiting on us to
supply the preliminary vertical alignments for wall slope stability and
wall design (if we need walls). We have begun drawing in the existing
water, sanitary sewer and storm sewer lines into our base files, based
upon the record drawings. We are also reviewing the private utility
files and trying to match them up with the flagging and paint marks.
After we get this information compiled we will begin looking at "rough"
horizontal and vertical alignment options to submit to you.
If you need any additional information or clarification, please feel
free to call me.
Quinn G. Spann, Jr., P.E.
Associate / Sr. Project Manager
GSWW, Inc.
11117 Shady Trail
Dallas, Texas 75229
972-620-1255 Ext 225
972-620-8028 Fax
(3/4/2010) Keith Marvin - RE: Deforest Road UpdatePage 1
From:
"Quinn Spann" <qspann@gswwengineers.com>
To:
"Keith Marvin" <kmarvin@ci.coppell.tx.us>
Date:
2/5/2008 4:23 PM
Subject:
RE: Deforest Road Update
I have not sent in a pay request yet. I will be working on that at the
end of the week, I hope. Do you have a set format for invoices? Is so,
can you send me a pdf. If not, I will just do it my normal way.
Quinn G. Spann, Jr., P.E.
Associate / Sr. Project Manager
GSWW, Inc.
11117 Shady Trail
Dallas, Texas 75229
972-620-1255 Ext 225
972-620-8028 Fax
-----Original Message-----
From: Keith Marvin [mailto:kmarvin@ci.coppell.tx.us]
Sent: Tuesday, February 05, 2008 4:09 PM
To: Quinn Spann
Cc: DiWanna Baskins; Dan DeGroot
Subject: Re: Deforest Road Update
Thanks for the update Quinn. We look forward to seeing some preliminary
alignment drawings in a few weeks.
I haven't seen a pay request yet on this project, have I? Please send
them to my attention when they come in.
Keith
Keith Marvin, P.E.
Project Engineer
(972) 304-3681
>>> "Quinn Spann" <qspann@gswwengineers.com> 2/5/2008 4:00 PM >>>
Keith,
The surveyor provided the survey to us on January 31st. The
Geotechnical has completed the borings. They are now waiting on us to
supply the preliminary vertical alignments for wall slope stability and
wall design (if we need walls). We have begun drawing in the existing
water, sanitary sewer and storm sewer lines into our base files, based
upon the record drawings. We are also reviewing the private utility
files and trying to match them up with the flagging and paint marks.
After we get this information compiled we will begin looking at "rough"
horizontal and vertical alignment options to submit to you.
(3/4/2010) Keith Marvin - RE: Deforest Road UpdatePage 2
If you need any additional information or clarification, please feel
free to call me.
Quinn G. Spann, Jr., P.E.
Associate / Sr. Project Manager
GSWW, Inc.
11117 Shady Trail
Dallas, Texas 75229
972-620-1255 Ext 225
972-620-8028 Fax