Bellacere Addn-CS080327(8/3112009) DiWanna Baskins - RE: Bellacere Addition - 300 W Sandy Lake Road
From: DiWanna Baskins
To: fluffy
CC: 'Tom Whatley'; twhatley~eaglemetal.com
Date: 3/27/200810:33 AM
Subject: RE. Bellacere Addition - 300 W Sandy Lake Road
Hello Micha,
The next step after the engineering reviews is for us to sign and approve the drawings, provided all fees are paid. You
would then schedule a preconstruction conference with the city.
It is in your best interest to finalize the mentioned items as you move forward with the reviews. Approximately how much
time do you need to get the geotechnical report and fire lane finalized?
-DiWanna
City of Coppell
Engineering Department
(P)972-304-3562
(F)972-304-3570
»> "fluffy" <michaduffyClcharter.net> 3/27/2008 9:43 AM »>
diwanna,
two items to discuss.
1, the thickness of paving - we have not completed the geotechnical work and
recommendations yet, can i place a notation on the Paving Plan that either
the 6" with the lime or a 7" PCC pavement will be used with the geotechnical
recommendationsN?
(In effect, this is what your standard note currently states "MIN.
REQUIREMENTS-UNLESS OTHERWISE APPROVED BY CITY ENGINEER")
2, we have not finalized the color/texture/etc on the pavement edge of the
fire lane, again, will a note suffice stating that engineering and fire
department shall approve the final design of the pavement edgeN?
thanks for your time.
these are the only two outstanding issues, i would like to get the plans
back to you today if possible.
yours truly,
micha p. fluffy, pe
HAMILTON DUFFY, PC
8241 mid cities blvd -suite 100
north richland hills, texas 76180-4759
817.268.0408 -phone
817.284.8408 -fax
entail - michaduffyCalcharter.net
Page 1
-----Original Message-----
From: DiWanna Baskins f mailto:dbaskinsClci.co~pell.tx.us1
Sent: Wednesday, March 05, 2008 2:50 PM
(8/3112009) DiWanna Baskins - RE: Bellacere Addition - 300 W Sandy Lake Road
To: fluffy
Cc: Tim Oates
Subject: RE. Bellacere Addition - 300 W Sandy Lake Road
Micha,
Yes, 7" or greater is a viable option. We would need for you to submit a
geotechnical report reflecting the same and a letter requesting a waiver if
you prefer not to lime stabilize the base.
I also spoke with Tim Oates, Deputy Chief with Fire Dept., regarding the
fire lane alternatives. We need for you to submit an example(s) of your
alternative option(s). So once you narrow them down, we can go from there.
Thanks
DiWanna Baskins
City of Coppell
Engineering Department
972-304-3562
»> "fluffy" <michaduffyClcharter.net> 3/5/200811.30 AM »>
diwanna,
here are a couple of options that we are looking at for the paving/fire lane
at Bellacere.
when we narrow all of our options, we will contact you to see if the City
(engineering and fire protection) is OK with the modifications.
question - is pavement thickness increase a valid option in lieu of lime
treated baseN?
yours truly,
micha p. fluffy, pe
HAMILTON DUFFY, PC
8241 mid cities blvd -suite 100
north richland hills, texas 76180-4759
817.268.0408 -phone
817.284.8408 -fax
entail - michaduffyCalcharter.net
Page 2