Bellacere Addn-CS080721(8/3112009) DiWanna Baskins - RE: Bellacere Addition - 300 W Sandy Lake Road
From: "fluffy" <michaduffy@charter.net>
To: "'DiWanna Baskins"' <dbaskins@ci.coppell.tx.us>
Date: 7/21/2008 5:13 PM
Subject: RE: Bellacere Addition - 300 W Sandy Lake Road
DiWanna
i think i might have found it.
Finished Floor must be a minimum of 1-ft above paving grade.
please verify.
yours truly,
micha p. fluffy, pe
HAMILTON DUFFY, PC
8241 mid cities blvd -suite 100
north richland hills, texas 76180-4759
817.268.0408 -phone
817.284.8408 -fax
entail - michaduffy@charter.net
-----Original Message-----
From: fluffy [mailto:michaduffy@charter.net]
Sent: Monday, July 21, 2008 4:36 PM
To:'DiWanna Baskins'
Subject: RE: Bellacere Addition - 300 W Sandy Lake Road
DiWanna,
i am trying to revive this project and get it back in your hands. is there
any way you can send me a PDF file of the latest engineering comments?
one of the specific questions that i have is about a comment referring to
the finished floorofthe homes. the comment referred to the minimum height
above the top of curb that the house needed to be.
1. i don't rememberwhat the minimum height was
2. i don't remember if it was the finished floor or finished pad of the
home.
Page 1
thank you for your time.
(8/3112009) Divvanna Baskins - RE: Bellacere Addition - 300 W Sandy Lake Road
yours truly,
micha p. fluffy, pe
HAMILTON DUFFY, PC
8241 mid cities blvd -suite 100
north richland hills, texas 76180-4759
817.268.0408 -phone
817.284.8408 -fax
entail - michaduffy@charter.net
-----Original Message-----
From: DiWanna Baskins [mailto:dbaskins@ci.coppell.tx.us]
Sent: Thursday, March 27, 200810:34 AM
To: fluffy
Cc: twhatley@eaglemetal.com; 'Tom Whatley'
Subject: RE: Bellacere Addition - 300 W Sandy Lake Road
Hello Micha,
The next step afterthe engineering reviews is for us to sign and approve
the drawings, provided all fees are paid. You would then schedule a
preconstruction conference with the city.
It is in your best interest to finalize the mentioned items as you move
forward with the reviews. Approximately how much time do you need to get
the geotechnical report and fire lane finalized?
DiWanna
City of Coppell
Engineering Department
(P)972-304-3562
(F)972-304-3570
»> "fluffy" <michaduffy@charter.net> 3/27/2008 9:43 AM »>
diwanna,
two items to discuss.
1. the thickness of paving - we have not completed the geotechnical work and
recommendations yet. can i place a notation on the Paving Plan that either
the 6"with the lime or a 7" PCC pavement will be used with the geotechnical
recommendations?
(In effect, this is what your standard note currently states "MIN.
REQUIREMENTS-UNLESS OTHERWISE APPROVED BY CITY ENGINEER")
2. we have not finalized the colorltexture/etc on the pavement edge of the
fire lane. again, will a note suffice stating that engineering and fire
department shall approve the final design of the pavement edge?
Page 2
(8/3112009) Divvanna Baskins - RE: Bellacere Addition - 300 W Sandy Lake Road
thanks for your time
these are the only two outstanding issues. i would like to get the plans
back to you today if possible.
yours truly,
micha p. fluffy, pe
HAMILTON DUFFY, PC
8241 mid cities blvd -suite 100
north richland hills, texas 76180-4759
817.268.0408 -phone
817.284.8408 -fax
entail - michaduffy@charter.net
-----Original Message-----
From: DiWanna Baskins [mailto:dbaskins@ci.coppell.tx.us]
Sent: Wednesday, March 05, 2008 2:50 PM
To: fluffy
Cc: Tim Oates
Subject: RE: Bellacere Addition - 300 W Sandy Lake Road
Micha,
Yes, 7" or greater is a viable option. We would need for you to submit a
geotechnical report reflecting the same and a letter requesting a waiver if
you prefer not to lime stabilize the base.
I also spoke with Tim Oates, Deputy Chief with Fire Dept., regarding the
fire lane alternatives. We need for you to submit an example(s) of your
alternative option(s). So once you narrow them down, we can go from there.
Thanks
DiWanna Baskins
City of Coppell
Engineering Department
972-304-3562
»> "fluffy" <michaduffy@charter.net> 315/200811:30 AM »>
diwanna,
here are a couple of options that we are looking at for the pavinglfire lane
at Bellacere.
Page 3
when we narrowall of our options, wewill contactyou to see ifthe City
(engineering and fire protection) is OK with the modifications.
(8/3112009) DiWanna Baskins - RE: Bellacere Addition - 300 W Sandy Lake Road
question - is pavement thickness increase a valid option in lieu of lime
treated base?
yours truly,
micha p. fluffy, pe
HAMILTON DUFFY, PC
8241 mid cities blvd -suite 100
north richland hills, texas 76180-4759
817.268.0408 -phone
817.284.8408 -fax
entail - michaduffy@charter.net
Page 4