WA9402A-CS080812~ w A q 4 b2. A- IRVING August 12, 2008 Ken Griffin, P.E. Director of Public Works City of Coppell 816 S. Coppell Road Coppell, Texas 75019 RE: DALLAS SUPPLY LINE #3 Dear Mr. Griffin: The Dallas Supply Line #3 water line is completely installed and operational. We have reviewed the total cost of constructing this line and submit to you the final invoices for the City of Coppell's commitment to Sections 3 A-1, A-2, 3 B, and the Elm Fork Meter Vault, including the associated SCADA system requirements. As per our agreement (City of Irving, Council Resolution No. 10-6-94-486), the City of Coppell has agreed to pay 20/91 or 21.98% of the costs for the aforementioned sections, beginning at the Elm Fork Water Treatment Plant and continuing to the Sandy Lake Road crossing. Section 3 A-1, approximately 2,230 feet of 60-inch diameter pipe Total Construction Cost = $1,155,776.20 City of Coppell commitment of 21.98% _ $254,039.61 Section 3 A-2, approximately 1,180 feet of 60-inch diameter pipe Total Construction Cost = $389,793 City of Coppell commitment of 21.98% _ $85,676.50 Section 3 B, approximately 2,245 feet of 60-inch diameter pipe Total Construction Cost = $1,018,295.40 City of Coppell commitment of 21.98% _ $223,821.33 Elm Fork Meter Vault Total Construction Cost = $1,280,000.00 City of Coppell commitment of 21.98% _ $281,344.00 SCADA System Requirements for Elm Fork Meter Vault Total Cost for 2 RTU's = $78,488.38 City of Coppell commitment of 21.98% _ $17,251.75 Public Works Department/ Water Utilities 333 Valley View Lane. Irving, Texas 75061 972.721.2281 972.721.2280 fax www.cityofirving.org August 12, 2008 DALLAS SUPPLY LINE #3 Page 2 After-Construction Maintenance Expense Section 5 of Article I of the Contract City of Coppell commitment of 21.98% _ $192,307.50 Right-of-Way Acquisition Costs Amount Paid: $117,580.00 City of Coppell commitment of 21.98% _ $25,841.76 Summary: Section 3 A-1 $254,039.61 Section 3 A-2 $85,676.50 Section 3 B $223,821.33 Elm Fork Meter Vault $281,344.00 SCADA S stem $17,251.75 After-Construction Maintenance Ex ense $192,307.50 ROW Ac uisition $25,841.76 Total $1,080,204.86 ! ~~s.~Z8~,45 Should you have any questions or need any additional information please let me know. Sincerely, ~~ ~,~ James C. Cline, Jr., P.E. Director of Public Works City of Irving -~~~~ CC Enclosure loin, 2~s~4o Zz3 ~~~ .33 X403 ,14 elw' ~ 2 64o3.?b 21 q $ t'3 , $S Cam ~'}~° 1;,~~.. ~ a~~- z 19 ~i4~ ,~S' 23~ 5 ~~ 57 I 1 v q t~ ~.S , ''~~ ~ ~ ~'~~~ , ~Z l ~~~w 1 6'~- ~$`f'~~ 24~ 11 b ~ '1'2- +„er~ ` ~"~` "' ~ 3bv , ']`~''2-9~5 ?4~R~~ ~2 ~ ~~ ~ ~~ ~~ ~ 121 ~" `7-~ _y 4'7 Q ~ Dc.~ 3 -_ - ;~ r~ ~