Arbor Manors-CS091020Matt Alexander
From: Brent Vilhauer [BVilhauer@rodmancompanies.com]
Sent: Tuesday, October 20, 2009 3:30 PM
To: Tom Ishmael; Matt Alexander; Barrett, Jeff
Subject: RE: Scans from Rodman Companies
If the City of Coppell would shut the street down by use of their barricades to allow us to
work the weekend starting Sat. nonstop, we could cut the cost by $16,380.00. This is a
combination of barricades and being able to work in the street without the time constraints.
Thanks
Brent Vilhauer
-----Original Message-----
From: Tom Ishmael
Sent: Wednesday, October 14, 2009 10:06 AM
To: Matt Alexander; Barrett, Jeff
Cc: Brent Vilhauer
Subject: FW: Scans from Rodman Companies
David WeekleyHomes. com
ia• ct• R ~'~ _ __
l~~b>sr MaMocs
S .S. 1,~~..~ ~, A c c t 9y
~It ow. 'fyt~ l7ac(~ y s
Jeff Barrett Houston: 713/316-3311
Director of Land Atlanta: 678/812.2051
Development Operations Fax: 770/569-0449
Mobile: 678/Z55.5384
j6arrettC~dwhomes.com
4385 Kimball Bridge Rd., Ste. 201 • Alpharetta, GA 30022
Matt / Jeff
Here is the quote for the change order on the San. Sewer line.
Tom Ishmael
Project Manager
214-908-5048
tishmael@rodmancompanies.com
-----Original Message-----
From: dpolk@rodmancompanies.com [mailto:dpolk@rodmancompanies.com]
Sent: Wednesday, October 14, 2009 10:59 AM
To: Tom Ishmael
Subject: Scans from Rodman Companies
This document was scanned directly from our NEC MFP. If you have any questions, please call
972-335-4510.
1
P.O. Box 957
6831 Ash St
Frisco, Tx 73034
Change Order
1 12" SpR 35 69 LF $ 350.00 $ 24,150.00
2 8" SbR 35 54 LF $ 90.00 $ 4,860.00
3 18" DIP Encasement 20 LF $ 80.00 $ 1,200.00
4 Concrete Encasement 20 LF $ 48.00 $ 960.00
5 Connect To Existin Manhole 4 EA $ 2,400.00 $ 9,600.00
6 Remove existin 8" sewer 123 LF $ 10.00 $ 1,230.00
7 Remove/Replace As halt Pavi 17 SY $ 225.00 $ 3 825.00
8 Testis 1 LS $ 1,500.00 $ 1,500.00
9 Trench Safet 1 LS $ 1 500.00 $ 1,500.00
10 Traffic Control 1 LS $ 7,500.00 $ 7,500.00
11 Maintenance Bond 1 LS $ 1,120.00 $ 1,120.00
Total: $ 57,445.00
Includes plugging existing manhole and bypass pumping sewer around in order to core 12" into
manhole.
Description 8 Reason for Change:
Remove existing 8" across Sandy Lake Rd and replace with 12" to correct existing elevation and flow _
problem.
Please call should you have any questions. Please sign and a-mail or fax back at (972) 712-3493.
Authorized Signature
Tom Ishmael Project Manager
Name 8 Title Name 8 Title
No. Description Qty Unlt M. Unit Extended