ST9905-MP080512ID Task Name Duration Start Finish T 1 PHASE I 204 days Thu 5/15108 Wed 1/7/09 1 2 BARRICADES 1 day Thu 5/15/08 Thu 5/15/08 3 EROSION CONTROL 2 days Fri 5/16/08 Sat 5/17/08 4 12 "WATER LINE 60 days Mon 5/19/08 Sat 7/26/08 5 STORM DRAIN 100 days Mon 5/19/08 Thu 9/11/08 6 REMOVALS 20 days Mon 7/28/08 Tue 8/19/08 7 EXCAVATION 20 days Wed 8/20/08 Thu 9/11/08 8 LIME STABILIZATION 30 days Fri 9/12/08 Thu 10/16/08 9 CONCRETE PAVEMENT 30 days Fri 10/17/08 Thu 11/20/08 10 INTERSECTIONS 20 days Fri 11/21/08 Sat 12/13/08 11 DRIVEWAYS 20 days Fri 11/21/08 Sat 12/13!08 12 INLET TOPS 20 days Fri 11/21/08 Sat 12/13/08 13 SIDEWALK & RAMPS 20 days Fri 11/21/08 Sat 12/13/08 14 ASPHALT TRANSITIONS 10 days Mon 12/15/08 Thu 12/25/08 15 BACKFILL 10 days Fri 12/26/08 Tue 1/6/09 16 SWITCH TRAFFIC 1 day Wed 1/7/09 Wed 1!7/09 17 18 PHASE II 130 days Thu 1/8/09 Mon 8/8/09 19 REMOVALS 10 days Thu 1/8/09 Mon 1/19/09 20 EXCAVATION 10 days Tue 1/20/09 Fri 1/30/09 21 STORM LATERALS 10 days Tue 1/20/09 Fri 1/30/09 22 LIME STABILIZATION 30 days Sat 1/31/09 Fri 3/6/09 23 CONCRETE PAVEMENT 30 days Sat 3/7!09 Fri 4/10/09 24 INTERSECTIONS 20 days Sat 4/11/09 Mon 5/4/09 25 DRIVEWAYS 20 days Sat 4/11/09 Mon 5/4/09 26 INLET TOPS 20 days Sat 4/11/09 Mon 5/4/09 27 SIDEWALK & RAMPS 20 days Sat 4/11/09 Mon 5/4/09 28 ASPHALT TRANSITIONS 10 days Tue 5/5/09 Fri 5/15!09 29 BACKFILL 10 days Sat 5116/09 Wed 5/27/09 30 STRIPING & SIGNAGE 10 days Thu 5/28/09 Mon 6!8/09 August Task ~~ Milestone • External Tasks Project: Base Split , , , , , , , , , Summary External Milestone Date: Mon 5/12/08 Progress Project Summary Deadline Page 1 ID Task Name Duration Start Finish -- Aug 10, 'OS Sep 21, '08 Nov 2, '08 M F T S W S T 1 BETHEL RD PHASE it 93 days? Thu 8/14/08 Sat 11/29/08 2 STAMPED CONCRETE 21 days Thu 8/14/08 Sat 9/6/08 ~ --_~ 3 SIGNALS 23 days Thu 8/14/08 Tue 9/9/08 4 SIDEWALK & RAMPS 26 days Mon 8/25/08 Thu 9/25/08 L_ 5 WALL 17 days Tue 9/2/08 Sat 9/20/08 0 6 PAVEMENT MARKINGS 15 days Tue 9/2!08 Thu 9/18/08 7 LANDSCAPE 54 days? Mon 9/15/08 Sat 11/15/08 -~~ 8 CLEANUP 12 days? Mon 11/17/08 Sat 11/29/08 Task ~ ~ Milestone • External Tasks Project: Schedule 8-14-08.mpp Split J Summa ry External Milestone Date: T hu8/14/08 ~~~~,.~~ ~~ ~~~~~ Progress Project Summary Deadline Page 1