SS9402B-CS 960306 P.O. Box 478
Col=pall, Texas 75019
The City With A Beautiful Future 214-462-0022
P.O. Box 478
Coppell. Texas 75019
March 6, 1996
Douglas Bisballe, Vice President
Pate Brothers Construction, Inc.
780 West Mansfield Highway
Kennedale, Texas 76060
Re: Grapevine IV Sanitary Sewer SS 94-02B Change Order g2
Dear Mr. Bisballe:
Attached to this letter is a Change Order which eliminntes the construction of the 12 inch sewer
line from approximately Station 24+37 to approximately Station 20+09. Thi~ is a distance of
428 feet. As we were investigating the most appropriate way to imtall the sewer line down
Bethel School Road across the existing box culvert, additionnl investi~ttion revealed that the line
was a 12" line, not an 8" line as the consulting engineer has shown on the construction plans.
When that was discovered, I instructed the Utility Department to televise the line to determine
the condition. That line was televised on February 27th, 1996 and it was determined that the
existing line was in adequate condition to be left in place.
The Change Order lists seven bids items which will be affected and the amount by which they
will be affected. I chose not to place any reduction in the contract on the change order until
such time as we have had an opportunity to negotiate per the terms of the contract. As you are
aware, the contract states that if any one bid item is 5 % of the total bid and then that particular
bid item is being adjusted by 20% either up or down, then either party can negotiate on that
particular bid item. In looking at the seven Bid Items, I determined that Bid Itetns//11 (12" SS
[10'-15' deep]); //12 (12" SS [15'-20' deep]); //19 (4' manhole); and #32 (R&R 8" concrete)
were all at least 5 % of the total bid and all had been adjusted by at least 20%. Bid Items 29,
36 & 38 will be adjusted according to the price bid on those items.
It is our goal to expedite this Change Order as soon as possible, therefore, the City stands ready
to meet with you to discuss the actual deduction on those particular bid items per the terms of
the contract.
I apologize for any inconvenience or confusion that this Change Order may have caused you.
Please contact this office as soon as possible so that this item can be resolved. If you should
have any questions please feel free to contact me at your convenience.
Sincerely,
KennL~eth M. Griffin, P.E.
Assistant City Manager/City Engineer
CHANGE OR EXTRA WORK ORDER
* NOTE: See Attached Letter
PROJECT: Grapevine IV Sanitary Sewer SS94-02B
CONTRACTOR: Pate Brothers Construction, Inc.
OWNER: City of Coppell
CHANGE ORDER NO.: 2 DATE: March 6, 1996
CHANGE OR EXTRA WORK TO BE DONE
Item Description Quantity Unit Unit Total
# Priee
DELETE: 11 12" SS (10'-15') 337.1 LF 31.52
12 12" SS (15'-20') 117.6 LF 40.80
19 4' Manhole 2 EA 2,597.01
29 Aband. SS MH 3 EA 763.43
32 R&R 8" Conc. 204 LF 59.33
36 R&R Rip Rap 9 SY 53.70
38 Trench Safety 395.7 LF 11.49
Total Revision to Contract Amount
Previous contract amount $
Net increase in contract amount $
Revised contract amount S
Net increase in contract time of completion N/A
Revised Contract time of completion N/A
The contractor hereby accepts this Contract adjustment as a final and complete adjustment in full
accord and satisfaction of nil past and future liability originating under any clause in the Contract
by reason of this revision to the Contract.