Below is an update on the few outstanding issues:
TxDOT frontage road - after review from the regional transportation group - TxDOT has once again
changed their mind and want to revert back to the original design of Point West intersecting the frontage
road/ramp at a T - therefore we will not have to realign/demo the road as currently constructed.
Traffic signal - battery backup - I have a call into Naztec to determine why it was not included, Andy
Watson, the sales mgr handling this project is on vacation until Monday. I'll provide an update as soon as
I am able to touch base with him.
Thanks-
Alex Bennett, P.E.