ST8601-CS 901004COPPELL PUBLIC WORKS
MEMORANDUM
DATE:
TO=
VIA~
FROM:
RE:
October 4, 1990
Steven G. Goram, Director of Public Works
M. Shohre Daneshmand, Acting City Engineer
Larry D av/~Construction Inspector
MacArthur North Extension - Inspection Fee
(Tickler 10/1/90)
The calculated construction cost for street construction and storm
drainage system on the above referenced project is $1,465,139.50,
based on the contract documents supplied by the engineering firm
of Carter and Burgess. The construction permit fee at 1.5% of
$1,465,139.50 would be $21,977.00.
The contract document construction time is based on 195 days from
the issuance of the letter to proceed. The approximate
construction inspection cost, for 195 days at an average of 3 hours
per day spent on the job site, would be estimated as listed below:
Inspection time
Vehicle expenses
Benefits
Plan review
Estimated inspection cost
$ 7,800.00
600.00
2,400.00
200.00
$11,000.00
If I can be of further assistance, please let me know.
Thank you.
CLD/bd
MACARTHU.CLD