Loading...
ST8601-CS 901004COPPELL PUBLIC WORKS MEMORANDUM DATE: TO= VIA~ FROM: RE: October 4, 1990 Steven G. Goram, Director of Public Works M. Shohre Daneshmand, Acting City Engineer Larry D av/~Construction Inspector MacArthur North Extension - Inspection Fee (Tickler 10/1/90) The calculated construction cost for street construction and storm drainage system on the above referenced project is $1,465,139.50, based on the contract documents supplied by the engineering firm of Carter and Burgess. The construction permit fee at 1.5% of $1,465,139.50 would be $21,977.00. The contract document construction time is based on 195 days from the issuance of the letter to proceed. The approximate construction inspection cost, for 195 days at an average of 3 hours per day spent on the job site, would be estimated as listed below: Inspection time Vehicle expenses Benefits Plan review Estimated inspection cost $ 7,800.00 600.00 2,400.00 200.00 $11,000.00 If I can be of further assistance, please let me know. Thank you. CLD/bd MACARTHU.CLD