SS9901A-PR011211Ken Griffin - Revised Pricin for t 3 0" Sanitary Sewer Line Pa 1
From: <dmergen @ccg mail. com>
To: City_ of _Coppell.Town_Center(kgriffin)
Date: Tue, Dec 11, 2001 4:34 PM
Subject: Revised Pricing for the 30" Sanitary Sewer Line
Ken,
The attachment in the message below covers the revised pricing for the 30"
sanitary sewer work that we discussed last week. We did not include any
costs for any required construction permits for this work because, as we
understand it, the permit costs may be waived in the agreement that the
City ultimately enters into with St Joseph Village, Inc. Please let me
know if you need any additional information. Thanks much.
Dan Mergen
Centex Construction Company
Forwarded by Daniel Mergen /CENTEX on 12/11/2001
04:20 PM ---------------
Daniel Mergen
12/10/2001 12:45 PM
To: jwd @orionrealty.com
cc:
Subject: Revised Pricing for the 30" Sanitary Sewer Line
The attachment contains revised pricing for the 30" sanitary sewer which is
based on our discussion last week with Mr. Griffin. Most of the decreases
from the previous estimate are attributable to decreases in the scope of
work, specifically decreases in the number of bends and length of pipe to
be installed. The unit pricing, except for that for "boring ", is the same
as in the previous estimate. The unit price for boring increased from $230
to $275 per lineal foot to reflect changing from a "wet' boring method to a
"dry" boring method which is the method the City typically specifies and
requires.
A new line item for surveying was added to the estimate in the amount of
$4,000 to cover the cost of setting controls for the installation of the
line.
A new line item was added in the amount of $6,000 for a payment and
performance bond for our subcontractor. A new line was also added in the
amount of $4,502 for a Centex Payment and Performance Bond. Mr. Griffin
had indicated that these bonds are typically required by the City.
(See attached file: Coppell - 30 inch Sanitary Sewer Estimate - 121001.xls)
CC: Allegro5.hub 05( "jwd @orion realty. com ")
Install 30" Sanitary Sewer Force Main
Scope of Work: Install a 1,990 If 30" ductile iron pipe sanitary force main in accordance with plans.
Description
QtV Unit
Unit price
Line Total
30" CL51 -D.I. Pipe 6'- 8' Cut
834 If
$
83.50
$
69,639
30" CL51 -D.I. Pipe 8' - 10' Cut
936 If
$
91.50
$
85,644
30" CL51 -D.I. Pipe 10'- 15' Cut
100 If
$
140.00
$
14,000
Bore 30" sewer
120 If
$
275.00
$
33,000
Air Release Valves
4 ea
$
2,450.00
$
9,800
Bends
12 ea
$
4,775.00
$
57,300
30" Plugs
2 ea
$
2,100.00
$
4,200
Trench Safety
1990 If
$
1.50
$
2,985
Testing
1990 If
$
1.50
$
2,985
Surveying
1 Is
$
4,000
subtotal
$
283,553
Subcontractor Payment and Performance Bond
$
6,000
subtotal
$
289,553
General Conditions
$
8,000
subtotal
$
297,553
Casualty Insurance
0.7908%
$
2,353
Builder's Risk Insurance
0.07%
$
208
subtotal
$
300,114
Centex Payment and Performance Bond
0.0%
$
-
subtotal
$
300,114
General Contractor's Fee
4.0%
$
12,005
Total
$
312,119
Coppell - 30 inch Sanitary Sewer Estimate - 121001
12/11/2001