SS9901A-PR021106St. Joseph Village / City Work
Pricing of Additional Scope of Work
Credit for Force Main Fitting Installation
C -Con
15,504
Subcontractor Payment & Performance Bond
310
General Conditions
0
Casualty Insurance
128
Builder's Risk Insurance
11
General Contractor's Fee
638
TOTAL
16,591
Add Soils Testing
HBC Engineering
2,200
Subcontractor Payment & Performance Bond
0
General Conditions
0
Casualty Insurance
0
Builder's Risk Insurance
0
General Contractor's Fee
0
TOTAL
2,200
Reduce Star Leaf Road width
Cooper (795 SY @ $3.00/ SY)
(2,652
TAS
(19,883
Asphalt 430 sf @ $2.17/sf
(933
Subcontractor Payment & Performance Bond
(53
General Conditions
0
Casualty Insurance
(22
Builder's Risk Insurance
(2)
General Contractor's Fee
(942)
TOTAL
24,487
City Portion 50%
(12,243
Add 12" water valve
C -Con
2,200
Subcontractor Payment & Performance Bond
44
General Conditions
0
Casualty Insurance
18
Builder's Risk Insurance
2
P�ELContractor's Fee
91
TOTAL
2,354
Add RCP under Star Leaf @ West P.L.
Area Excavation
43,000
Credit Original Storm Water
6,716
Subtotal
36,284
Subcontractor Payment & Performance Bond
726
General Conditions
0
Casualty Insurance
299
Builder's Risk Insurance
26
General Contractor's Fee
1,493
TOTAL
38,828
Add for paving machine - City's Portion
TAS
26,471
Subcontractor Payment & Performance Bond
529
General Conditions
0
Casualty Insurance
218
Builder's Risk Insurance
19
General Contractor's Fee
1,090
TOTAL
28,327
City Portion 20%
5,665
Delete Sidewalk on South /East side of Star Leaf Road
TAS
4,311
Subcontractor Payment & Performance Bond
86
General Conditions
0
Casualty Insurance
35
Builder's Risk Insurance
3
General Contractor's Fee
177
City's Portion TOTAL
4,613
VC1,0
11,6•?.