JANUARY 22, 2010 SERVING COPPELL, VALLEY RANCH AND H ACKBERRY CREEK SINCE 1984 VOLUME XXVI, No. 4
E- Cycling Set
for Saturday
By Jane Moore
The City of Coppell will
offer drop -off recycling of
electronic equipment, includ-
ing cell phones, computers
and televisions, this Saturday,
January 23, from 9:00 a.m.
to noon at Town Center, 255
Parkway Boulevard. The
event is organized by Keep
Coppell Beautiful.
Computers, phones and
related equipment may be
recycled free of charge.
There will be a $7 cash -only
fee for computer monitors
and a $12 fee for televisions.
The City offers e- cycling
several times a year.
For more information, call
972 - 462 -5100.
Road Construction Progresses on South Side
By Jean Murph
Road work is making pro-
gress in south Coppell, accord-
ing to City Manager Clay Phillips
during a recent Council meeting,
with concrete poured on S.
Coppell Road and a timeline of
about six to eight weeks until
completion.
On Southwestern Boulevard,
concrete has been poured from
S. Coppell Road to the bridge,
which has been reconstructed.
The other half of the bridge will
be poured soon, and the City is
anticipating an August 1 comple-
tion date, said Phillips.
Traffic is being rerouted for
the S. Coppell Road project, but
Southwestern Boulevard re-
mains open, with new construc-
tion occuring parallel to the old
Concrete has been poured on half of the new bridge on Southwestern
see ROAD on page 8 construction moves forward. (See more photos on page 8.)
pltoto oy Hatey Moore
Boulevard, as road
from page i
road.
Right -of -way issues on W. Sandy
i SUP Rnnrl.u7iII „PPM to he resolved be-
fore the road project can be completed,
said Phillips.
The City's pavement replacement pro-
gram is underway and in the design phase,
he said.
Southwestern Boulevard construction work will be in two phases, with con-
crete to be poured on the other half of the bridge soon.
The S. Coppell Road reconstruction project will oe compim 1 11 01^ •� `•