Duke Lesley 3A-CS100122DEVELOPMENT FEE TABLE
Project: Duke Lesley Lot 3 Blk A
Date: 1111012009
TOTAL
AMOUNT DUE
FEES DUE
PRIOR TO
FILING
11
11 PLAT
Water Impact Fee
$2,997.00
(100% due at Issuance of Building Permit)
Water Tap Inspection Fee
$50.00
(100% due at Issuance of Water Meter)
Water Meter Fee (Domestic)
$0.00
(100% due at Issuance of Water Meter)
Water Meter Fee (Irrigation/Fireline)
$251.04
(100% due at Issuance of Water Meter)
Water Meter Deposit (Domestic)
$0.00
(100% due at Issuance of Water Meter)
Irrigation/Fireline Meter Deposit
$30.00
(100% due at Issuance of Water Meter)
Wastewater Impact Fee
$0.00
(100% due at Issuance of Building Permit)
Wastewater Tap Inspection Fee
$0.00
(100% due at Issuance of Building Permit)
Utility Final Inspection Fee
$0.00
(100% due at Issuance of Building Permit)
Park Fee
$0.00
$0.00
(100% due prior to Filing Plat)
Roadway Impact Fee
$0.00
$0.00
(100% due prior to Filing Plat)
Street Light Fee
Information not Available
(100% due prior to Acceptance of Project)
Street Sign Fee
Information not Available
(100% due prior to Acceptance of Project)
r onstruction Inspection Fee
Information not Available
(100% due prior to Start of Construction)
TOTAL
$3,328.04
.140 no
TOTAL AMOUNT DUE PRIOR TO FILING FINAL PLAT
DEVELOPMENT FEE WORKSHEET
PROJECT: Drrke Lesley Lot 3 Blk A
DATE: 1111012009
Water Impact Fee:
Domestic Meter(s):
Irrigation Meter(s):
Fireline Meter(s):
U
1 - 1 1/2 inch
0
I
u
Total #: 3.33 ESU's @ $900.00 ea.
(Due prior to issuance of building permit)
= 0
ESU's
= 3.33
ESU's
= 0
ESU's
= 0
ESU's
Water Tap Inspection Fee:
Total #: 1 Connections @ $50.00 ea.
(Single family due prior to issuance of building permit)
(All other developments due prior to issuance of meter)
Domestic Water Meter Fee:
Total #: 0 Domestic Meter(s) @ $0.00
(Single family due prior to issuance of building permit)
(All other developments due prior to issuance of meter)
Irrigation /Fireline Water Meter Fee:
$2,997.00
$50.00
$0.00
Total #: 1 Irrigation Meter(s) @ $251.04 $251.04
Total #: 0 Additional Irrigation Meter(s) @ $0.00 $0.00
Total #: 0 Fireline Meter(s) @ $0.00 meter provided by developer
(100% due prior to issuance of water meters)
Domestic Water Meter Deposit Fee:
Total #: 0 Meter(s) @ $30.00 ea.
(100% due prior to issuance of water meters)
Irrigation /Fire Meter Deposit Fee:
Total #: 1 Meter(s) @ $30.00 ea.
(100% due prior to issuance of water meters)
Wastewater Impact Fee:
Total Domestic Meters ESU's: 0
(Due prior to issuance of building permit)
@ $900.00 ea.
Wastewater Tap Inspection Fee:
Total #: 0 Connections @ $50.00 ea.
(100% due prior to issuance of building permit)
Utility Final Inspection Fee (All developments):
Total #: 0 Lots @ $50.00 ea.
(100% due prior to issuance of building permit)
Park Fee (For Residential Developments Only):
Page 1
$0.00
$30.00
$0.00
Gl 1 11
$0.00
DEVELOPMENT FEE WORKSHEET
* Preliminary plat approved:
0 Single- family @ $0.00 per lot $0.00
0 Multi- family @ $0.00 per unit $0.00
(100% paid prior to Council approval of final plat)
Roadway Impact Fee:
(See attached fee calculations) $0.00
Street Lighting Fees:
Assessed for lighting in the City's right -of -way. Information not Available
This fee cannot be assessed until after T.U. Electric submits
the lighting plan for the proposed development.
Once the plans are submitted, $292.60 per light will be assessed.
(100% due prior to final acceptance of development)
Street Sign Fees:
Assessed for signage in the City's right -of -way. Information not Available
(See attached fee calculations if applicable)
Construction Inspection Fees:
A copy of the development contract must be submitted for assessment. Information not Available
The contracts should indicate the cost to construct the improvements
that are inspected by the Engineering Department.
(2% of development cost required for private improvements)
(4% of development cost required for public improvements)
Page 2