RE: North Gateway Plaza Lot 9 B1k.A
Fee Assessment Letter — Revised 2/5/2010
Dear Mr. Wouters:
Enclosed is a copy of the City of Coppell Development Fee Assessment table, along with a copy of the
Development Fee calculations for the referenced development.
This document has been revised to reflect the size and number of water meters shown in the final
engineering documents dated 8/5/2009.
The fees for water and sewer taps, water meters, and utility inspection fees need to be paid by separate
check at the Public Works Service Center, 816 S. Coppell Road. Meters will be ordered when those fees
are paid.
Appropriate payment of the required fees will help insure a successful project. We look forward to
working with you on this project. If you have any questions, please contact me.
Sincerely,
Keith R. Marvin, P.E.
Project Engineer
cc: Jennifer Miller, Finance Director
Mary Beth Spletzer, Administrative Secretary, Building Inspections
Glenn Hollowell, Assistant Director of Public Works
Tim Oates, Deputy Chief /Prevention
Brad Reid, Director of Parks and Recreation
255 PARKWAY * P.O.BOX 9478 * COPPELL TX 75019 * TEL 972/462 0022 * FAX 972/304 3673
DEVELOPMENT FEE TABLE
Project: North Gateway Plaza Lot 9 Blk. A
Date: 611712009,rev (612912009),rev 2/5/2010
TOTAL
AMOUNT DUE
FEES DUE
PRIOR TO
FILING
11 11
PLAT
Water Impact Fee
$5,256.00
(100% due at Issuance of Building Permit)
Water Tap Inspection Fee
$200.00
(100% due at Issuance of Water Meter)
Water Meter Fee (Domestic)
$119.73
(100% due at Issuance of Water Meter)
Water Meter Fee (Irrigation/Fireline)
$119.73
(100% due at Issuance of Water Meter)
Water Meter Deposit (Domestic)
$30.00
(100% due at Issuance of Water Meter)
Irrigation/Fireline Meter Deposit
$90.00
(100% due at Issuance of Water Meter)
Wastewater Impact Fee
$1,503.00
(100% due at Issuance of Building Permit)
Wastewater Tap Inspection Fee
$50.00
(100% due at Issuance of Building Permit)
Utility Final Inspection Fee
$50.00
(100% due at Issuance of Building Permit)
Park Fee
$0.00
$0.00
(100% due prior to Filing Plat)
Roadway Impact Fee
$0.00
$0.00
(100% due prior to Filing Plat)
Street Light Fee
Information not Available
(100% due prior to Acceptance of Project)
Street Sign Fee
Information not Available
(100% due prior to Acceptance of Project)
Construction Inspection Fee
Information not Available
(100% due prior to Start of Construction)
TOTAL
$7,418.46
$0.00
TOTAL AMOUNT DUE PRIOR TO FILING FINAL PLAT
DEVELOPMENT FEE WORKSHEET
PROJECT: North Gateway Plaza Lot 9 Wk. A
DATE: 611712009,rev (612912009),rev (21512010)
Water Impact Fee:
Domestic Meter(s):
1 - 1 inch
= 1.67
ESU's
Irrigation Meter(s):
1 - 1 inch
= 1.67
ESU's
0
= 0
ESU's
Fireline Meter(s):
2 - 8 inch
= 2.5
ESU's
Total #: 5.84 ESU's @ $900.00 ea.
(Due prior to issuance of building permit)
Water Tap Inspection Fee:
Total #: 4 Connections @ $50.00 ea.
(Single family due prior to issuance of building permit)
(All other developments due prior to issuance of meter)
Domestic Water Meter Fee:
Total #: 1 Domestic Meter(s) @ $119.73
(Single family due prior to issuance of building permit)
(All other developments due prior to issuance of meter)
Irrigation /Fireline Water Meter Fee:
$5,256.00
$200.00
$119.73
Total #: 1 Irrigation Meter(s) @ $119.73 $119.73
Total #: 0 Additional Irrigation Meter(s) @ $0.00 $0.00
Total #: 2 Fireline Meter(s) @ n/a meter provided by developer
(100% due prior to issuance of water meters)
Domestic Water Meter Deposit Fee:
Total #: 1 Meter(s) @ $30.00 ea.
(100% due prior to issuance of water meters)
Irrigation /Fire Meter Deposit Fee:
Total #: 3 Meter(s) @ $30.00 ea.
(100% due prior to issuance of water meters)
Wastewater Impact Fee:
Total Domestic Meters ESU's: 1.67
(Due prior to issuance of building permit)
@ $900.00 ea
Wastewater Tap Inspection Fee:
Total #: 1 Connections @ $50.00 ea.
(100% due prior to issuance of building permit)
Utility Final Inspection Fee (All developments):
Total #: 1 Lots @ $50.00 ea.
(100% due prior to issuance of building permit)
Park Fee (For Residential Developments Only):
$30.00
$90.00
$1,503.00
$50.00
$50.00
Page 1
DEVELOPMENT FEE WORKSHEET
* Preliminary plat approved: After October 26, 1993
0 Single- family @ $0.00 per lot
0 Multi- family @ $0.00 per unit
(100% paid prior to Council approval of final plat)
Roadway Impact Fee:
(See attached fee calculations)
Street Lighting Fees:
Assessed for lighting in the City's right -of -way.
This fee cannot be assessed until after T.U. Electric submits
the lighting plan for the proposed development.
Once the plans are submitted, $292.60 per light will be assessed.
(100% due prior to final acceptance of development)
Street Sign Fees:
Assessed for signage in the City's right -of -way.
(See attached fee calculations if applicable)
Construction Inspection Fees:
A copy of the development contract must be submitted for assessment.
The contracts should indicate the cost to construct the improvements
that are inspected by the Engineering Department.
(2% of development cost required for private improvements)
(4% of development cost required for public improvements)
$0.00
$0.00
$0.00
Information not Available
Information not Available
Information not Available
Page 2
ROADWAY IMPACT FEE CALCULATIONS
PROJECT: North Gateway Plaza Lot 9 Blk. A
DATE: 611712009,rev (612912009),rev (21512010)
ROADWAY IMPACT FEE:
Service Area *
I
Category **
Office
Land Use **
General Office Buildin
Building Area (sf)
8,100
Develo ment Units **
8.10
Vehicle Miles per Development Unit **
7.15
Fee per Vehicle Mile * **
$150
Roadway Impact Fee due = (Development Units) x
(Vehicle Miles per Development Unit) x (Fee per Vehicle Mile) _ $8,687.25
* (Figure 4.1 - Roadway Impact Fee Study)
** (Table 4.10 - Roadway Impact Fee Study)
* ** (Schedule 2, Page 3 - The Master Fee Schedule)
Percent of Credit Toward Roadway Impact Fees 100%
Total Credit $8,687.25
Credit per Developers Agreement May 19,1998