WA9402-CS 9607011 July, 1996 07-08-96A09:09 RCVD Dave Mullins City of Irving Engineering Dept. 825 W. Irving Blvd. Irving, TX Re: Request for additional compensation for Dallas Water Supply Line No.3 project Mr. Mullins, As you are aware J.C. Evans Construction Co. has experienced a substantial loss of productivity while trying to complete the installation of the cased bore at station 114+40 on the above referenced project. We are therefore requesting compensation for this loss in the amount of $61,703.40 and additional time on the contract in the amount of 16 calendar days. It is our stance that the situation that caused this delay constitutes a change of conditions to the project and thereby merits the appropriate adjustment to the contract. Specifically, the change of conditions referenced above is the location of the 45° bend on the existing 12" waterline. location of this bend is the only causative factor for all a~nal c~ts incurred. The direction of thrust from the east to west, towards the excavation for the bore pit, instead of east to west away from the bore excavation provided the only opportunity for the blow out that occurred in spite of the fact that the excavation was fully 20' away form the bend. Further exacerbating the potential for a blow out was the fact that the 12" waterline was at an elevation fully 9' higher than indicated which increased the opportunity for a blow out due to a sloughing effect. Had this waterline been located as shown on the drawings, thrusting away from the excavation the blow out would never have occurred. So that you may be better able to confirm that the requested amount of compensation is due I am providing you with the timeline and a detailed cost list for equipment, labor and materials on Attachments A, B and C. Should you have any questions regarding this request you may contact myself or Ruben Garza at (214)257-0639. Thank you in advance for your timely response on this matter. Sincerely, 3900 Valley View Ln. · Irving, Texas 75062 · (214) 257-0639 . ATTACHMENT "A" TIMELINE June 18 -- Begin installing 60" pipe in bore. June 20 -- 12" Waterline blows out filling casing and pipe with mud June 21 thru 26 -- Remove pipe From bore, clean casing and prep to reinstall. Waterline blows again the evening of June 26. June 27 & 28 -- Remove pipe from bore, clean casing and prep to reinstall. June 29 -- Saturated ground causes thrust block to move on existing 30" CCP and it begins blowing. June 29 & 30 -- Repair 30" waterline. July I thru 3 -- Remove pipe, clean casing and prep to re-install. ATTACHMENT "B" EQUIPMENT/MATERIAL COSTS DATE EQUIPMENT DALLY COST DAYS EXTENSION June 18 thru June 26 Hitachi 550 $ 1,240.00 8 $ 9,936.00 Cat 963 $ 460.00 8 $ 3,680.00 Kamatsu 250 $ 295.00 8 $ 2,355.00 Kamatsu 300 $ 425.00 8 $ 3,400.00 6" Pump $ 280.00 8 $ 2,240.00 Generator $ 35.00 8 $ 280.00 _~i I '~ Trenchboxes $ 45.00 8 $ 360.00 June 27 thin July 3 Hitachi 550 $ 1,240.00 6 $ 7,440.00 Cat 963 $ 460.00 6 $ 2,760.00 Kamatsu 250 $ 295.00 6 $ 1,770.00 '~ d;~ R-12 Roller $ 280.00 6 $ 1,680.00 ,,,L- ~ O~"'ZO 6"Pump $ 280.00 6 $ 1,680.00 Generator $ 35.00 6 $ 210.00 Trenchboxes $ 45.00 6 $ 270.00 ~ ~ Watertank $ 65.00 6 $ 390.00 Total Equipment Costs $40,691.00 1.110 l.f. 12" PVC C-900 waterline at 12.93/1.f. $ 1,422.30 2. 1 ea. 12" 45 degree bend with megalugs $ 188.10 3.5 c.y. of concrete at $60.00 $ 300.00 4. 2 ea. 4' x 12' sheet pilings at $150.00 ea. $ 300.00 Total Materials Costs $ 2,210.40 ATTACHMENT "C" LABOR COSTS JOB TITLE HOURLY RATE TOTAL HOURS EXTENSION Superintendent $25.00 163.0 $ 4,075.00 Operators $15.00 303.0 $ 4,545.00 Laborers $12.00 848.5 $10, 182.00 Total Labor Costs $18,802.00 TOTAL ADDITIONAL REQUEST $61,703.40 c ,x ,,~.4-hrs '- ~ o ~,---,