Ken Griffin - RE: Alexander Court LOMR
From: "philberkebile" <philberkebile@verizon.net>
To: "'Ken Griffin'" <kgriffin@ci.coppell.tx.us>
Date: 4/3/2008 3:17 PM
Subject: RE: Alexander Court LOMR
Ken,
Did the 100yr flood plain elevation drop to 493’ (or whatever the lower level was)?
Phil
From: Ken Griffin [mailto:kgriffin@ci.coppell.tx.us]
Sent: Thursday, April 03, 2008 1:52 PM
To: philberkebile
Subject: Re: Alexander Court LOMR
Phil
We received the approved study from FEMA on 3/24/08. It generally follows what was submitted.
Ken Griffin
>>> "philberkebile" <philberkebile@verizon.net> 4/3/2008 12:54 PM >>>
Ken,
Just checking back. Any word from Hawkins or Nathan Maier Engineering regarding the LOMR approval for the Alexander
Court development? Assuming it has not yet been received by the City, has Hawkins given you a new ETA? Thanks.
Phil Berkebile
From: Ken Griffin [mailto:kgriffin@ci.coppell.tx.us]
Sent: Friday, March 14, 2008 1:10 PM
To: philberkebile
Subject: Re: Meeting
Phil
I've got some time around 2-2:30 today if you want to stop by.
Ken Griffin
>>> "philberkebile" <philberkebile@verizon.net> 3/14/2008 12:18 PM >>>
Ken,
Jeffrey Alvarez from Robert Halff and I would like to meet with you as soon as possible to discuss the development of our
property at 239 W. Bethel. Do you have some time this afternoon? Both Jeffrey and I are out of town next week and we
have some questions regarding floodplain/floodway as they relate to our project. Let me know. Thanks.
Phil Berkebile