Thanks, Ken. Just to be clear on the outcome of our meeting on 3/14/08, since Mr. Berkebile's
proposed property will fall just outside of the floodplain as a result of the approved LOMR base flood
elevation of 493 through the property, a Letter of Map Amendment (LOMA) to FEMA is all that you
will require to prove that it will in fact be out of the floodplain, is that correct? Given this new LOMR
approval information for Alexander Court, please let me know if there is anything else you will require
other than the LOMA to allow Mr. Berkebile's property development to proceed.
Thank you.
Jeffrey A.
Jeffrey J. Alvarez, P.E.
Project Manager
HALFF ASSOCIATES, INC.
3801 Parkwood Blvd., Suite 500
Frisco, Texas 75034
Phone 214-618-4570
Fax 214-618-4574
www.halff.com
From: Ken Griffin [mailto:kgriffin@ci.coppell.tx.us]
Sent: Friday, April 04, 2008 12:30 PM
To: Alvarez, Jeffrey
Subject: RE: Alexander Court LOMR
Jeffrey
The FEMA information for Alexander Court is attached. If you have any questions, contact me at your
convenience.
Ken Griffin, P. E.
Director of Engineering & Public Works
972-304-3686
kgriffin@ci.coppell.tx.us
>>> "Alvarez, Jeffrey" <JAlvarez@Halff.com> 4/4/2008 11:07 AM >>>
Ken I will come by this afternoon and pick up the information if that is okay. Please let me
know.
Thanks.
Jeffrey A.
file://C:\Documents and Settings\radloo\Local Settings\Temp\XPgrpwise\47F643DFCity_...2/19/2010
Page 2 of 3
From: philberkebile [mailto:philberkebile@verizon.net]
Sent: Friday, April 04, 2008 11:06 AM
To: 'Ken Griffin'
Cc: Alvarez, Jeffrey
Subject: RE: Alexander Court LOMR
Thanks Ken.
Jeffrey Alvarez from Halff Associates will follow-up with you on my behalf and I'm sure he will want to pick up
copies of the new information.
Regards,
Phil
From: Ken Griffin [mailto:kgriffin@ci.coppell.tx.us]
Sent: Friday, April 04, 2008 9:22 AM
To: philberkebile
Subject: RE: Alexander Court LOMR
Yes. You can stop by and pick up the revised information, if that would be helpful to you.
Ken Griffin
>>> "philberkebile" <philberkebile@verizon.net> 4/3/2008 3:14 PM >>>
Ken,
Did the 100yr flood plain elevation drop to 493' (or whatever the lower level was)?
Phil
From: Ken Griffin [mailto:kgriffin@ci.coppell.tx.us]
Sent: Thursday, April 03, 2008 1:52 PM
To: philberkebile
Subject: Re: Alexander Court LOMR
Phil
We received the approved study from FEMA on 3/24/08. It generally follows what was submitted.
Ken Griffin
>>> "philberkebile" <philberkebile@verizon.net> 4/3/2008 12:54 PM >>>
Ken,
Just checking back. Any word from Hawkins or Nathan Maier Engineering regarding the LOMR approval for the
Alexander Court development? Assuming it has not yet been received by the City, has Hawkins given you a new
ETA? Thanks.
Phil Berkebile
file://C:\Documents and Settings\radloo\Local Settings\Temp\XPgrpwise\47F643DFCity_...2/19/2010
Page 2 of 2
Phil Berkebile
From: Ken Griffin [mailto:kgriffin@ci.coppell.tx.us]
Sent: Friday, March 14, 2008 1:10 PM
To: philberkebile
Subject: Re: Meeting
Phil
I've got some time around 2-2:30 today if you want to stop by.
Ken Griffin
>>> "philberkebile" <philberkebile@verizon.net> 3/14/2008 12:18 PM >>>
Ken,
Jeffrey Alvarez from Robert Halff and I would like to meet with you as soon as possible to discuss the
development of our property at 239 W. Bethel. Do you have some time this afternoon? Both Jeffrey and I are out
of town next week and we have some questions regarding floodplain/floodway as they relate to our project. Let
me know. Thanks.
Phil Berkebile
(972) 898-5689 cell
philberkebile@verizon.net