Loading...
SS9402A-CS 960326 CITY OF COPPELL CHANGE OR EXTRA WORK ORDER PROJECT: Grapevine III Sanitary Sewer Project / SS 94-02A CONTRACTOR: River Valley Enterprises ADD: OWNER: City of Coppell CHANGE ORDER NO.: 1 DATE: CHANGE OR EXTRA WORK TO BE DONE Pay Description Quantity Unit ltem# 5 32 LF 38 42 43 44 45 March 26, 1996 Unit Price Furnish & Place 8" PVC Sewer (I 5'-20' depth) 45.00 Trench Excavation Safety Concrete Channel ReplaCement Remove Existing 8" SS Concrete Fill Existing 4'MH Lower Invert Elevation 32 50 26 LF 2.00 Lr 34. LF EA {~ ~5'~- ~ EA Total Revision to Contract Amount Total d, ~/' ~ J q ,~,.5. Previous contract amount Net increase in contract alnount Revised contract amount Net increase in contract time of completion Revised Contract time of completion $ 365,124.00 ,~. 70'Z.~ The contractor hereby accepts this Contract adjustment as a final and complete adjustment in full accord and satisfaction of all past and future liability originating under any clause in the Contract by reason of this revision to the Contract. Recommended by the City Engineer: Date: Agreed to by the Contractor: Accepted by the Owner: Date: