SS9402C-AG 960514 REQUEST FORM
CITY COUNCIL MEETING: Ma~,1996 ITEM #
ITEM CAPTION: /! ~
Approval of Change Order #1 for lhe Bethel Road Sanitary Sewer Project' (SS 9~02C) to Pate Brothers
Co~ Company authorizing the Mayor to sign.
SUB~D BY: Kenneth M.
TITLE: Assistant
STAFF COMMENTS:
See attached memo.
STAFF RECO~~A~ON
EXPLANATION:
Staff will be available to answer any
P.E.
I~ITIALS ~
at the Council meeting.
BUD(~ET AMT. $
FINANCIAL COMMENTS:
FINANCIAL REVIEW:
Agenda Request Form - Revised 1/94
EST.$
+/- BUD:$
CITY MANAGER REVIEW:
Document Name eng.02
From:
MEMORANDUM
Mayor and City Council
Kenneth M. Griff'm, P.E., ACM/City Engineer
Approval of Change Order #1 for the Bethel Road Sanitary Sewer Project
(SS 94-02C) in the amount of $142,775.89 to Pate Brothers Construction
and authorizing the Mayor to sign.
Date: May 7, 1
For approximately eight
Engineering Finn of HDR
Parkway west to the Bulk
design had approximately a
City was unable to take the
of the last 3,200 feet of this se'
the easement on the Bulk
service.
now the City of Coppell has been negotiating with the
a resolution to the sewer line design in Bethel Road from Freeport
Facility Lift Station. Council may be aware that the original
foot error and by constructing the sewer line as designed, the
Postal Facility Lift Station out of service. Obviously, the goal
line was to remove that lift station. The City also acquired
Facility under the pretense of taking the lift station out of
Various alternatives have been
attempted to limit their
a resolution on this issue, the City
contract directly with a separate
the City's contractor, Pate Brothers
a flatter grade. The original design was
for a 15 inch sewer line. There was
installed approximately 475 feet of sewer
worked, then Pate Brothers would have had
relay it at a different grade to make sure
However, the sewer line design did not
the 970 feet and relayed it, HDR would have
a 15 inch sewer line. It is my contention
Coppell and regardless of what Pate Brothers
install the line flat, as they did, HDR would
Freeway and enlarge it to a 15 inch sewer line.
by HDR, however, in each alternative HDR has
approximately $100,000. To assist HDR in coming to
Coppell offered HDR the opportunity to negotiate and
to remove the sewer line that had been installed by
Company and reinstall a larger sewer line on
a 10 inch sewer line and the proposed design is now
discrepancy over the fact that Pate Brothers had
flat and that if the original design would have
remove approximately 970 feet of sewer line and
there was positive flow in the sewer line.
as such, even if Pate Brothers had removed
to come back and remove it and replace it with
HDR provided a faulty design to the City of
have done i.e., install the line on grade or
had to remove the line all the way back to
HDR's position is that the City should direct Pate
this 970 foot area and relay it as a 15 inch line
advantage of that and then only pay the difference
inch. It should be noted that there are no bid items
and the City would have to negotiate the price with Pate
President of Pate Brothers stated that if he was
would do so as a 10 inch line on the grade proposed by
to remove the 10 inch line through
a different grade so that HDR can take
cost between the 10 inch and the 15
project for a 15 inch sewer line pipe
When questioned, the Vice-
remove and relay the 970 feet he
the original design. Obviously,
by taking that approach, the entire 970 feet would have to be removed a second time and relayed
as a 15 inch sewer line.
It appears at this point because of HDR's reluctance to exceed a self imposed $100,000 limit and
the City of Coppell's inability to exceed $15,000 under State Purchasing Guidelines without
bidding, that this project is at an impasse. Therefore, the position taken by the City of Coppell
is to cease negotiations with the Firm of HDR, remove the 10 inch line that was erroneously
designed, relay a 15 inch line and then seek remedy from HDR in court to recoup the City's
cost.
Based on the above facts, staff recommends the approval of Change #1 to Pate Brothers in the
amount of $142,775.89 and will be available to answer any questions at the Council meeting.
C i The City With A Beautiful Future
0 AGENDA REQUEST FORM
CITY COUNCIL MEETING: May 14, 1996
ITEM #
ITEM CAPTION:
Approval of Change Order#1 for the Bethel Road Sanitary Sewer Project (SS 94-02C) to Pate Brothers
Construction Company and authorizing the Mayor to sign.
SUBMITTETED BY: Kenneth M. Griffin, P.E.
TITLE: Assistant City Manager/City Engineer INITIALS
STAFF COMMENTS:
See attached memo.
STAFF RECOMMENDATION Approval X Denial
EXPLANATION:
Staff will be available to answer any questions at the Council meeting.
BUDGET AMT.$ AMT. EST.$ +/— BUD:$
FINANCIAL COMMENTS:
FINANCIAL REVIEW: CITY MANAGER REVIEW:
Agenda Request Form-Revised 1/94 Document Name eng.02
MEMORANDUM
To: Mayor and City Council
From: Kenneth M. Griffin, P.E., ACM/City Engineer
RE: Approval of Change Order #1 for the Bethel Road Sanitary Sewer Project
(SS 94-02C) in the amount of $142,775.89 to Pate Brothers Construction
Company and authorizing the Mayor to sign.
Date: May 7, 1996
For approximately eight weeks now the City of Coppell has been negotiating with the
Engineering Finn of HDR on a resolution to the sewer line design in Bethel Road from Freeport
Parkway west to the Bulk Postal Facility Lift Station. Council may be aware that the original
design had approximately a two foot error and by constructing the sewer line as designed, the
City was unable to take the Bulk Postal Facility Lift Station out of service. Obviously, the goal
of the last 3,200 feet of this sewer line was to remove that lift station. The City also acquired
the easement on the Bulk Postal Facility under the pretense of taking the lift station out of
service.
Various alternatives have been submitted by HDR, however, in each alternative HDR has
attempted to limit their responsibility to approximately $100,000. To assist HDR in coming to
a resolution on this issue, the City of Coppell offered HDR the opportunity to negotiate and
contract directly with a separate contractor to remove the sewer line that had been installed by
the City's contractor, Pate Brothers Construction Company and reinstall a larger sewer line on
a flatter grade. The original design was for a 10 inch sewer line and the proposed design is now
for a 15 inch sewer line. There was some discrepancy over the fact that Pate Brothers had
installed approximately 475 feet of sewer line flat and that if the original design would have
worked, then Pate Brothers would have had to remove approximately 970 feet of sewer line and
relay it at a different grade to make sure that there was positive flow in the sewer line.
However, the sewer line design did not work and as such, even if Pate Brothers had removed
the 970 feet and relayed it, HDR would have had to come back and remove it and replace it with
a 15 inch sewer line. It is my contention that HDR provided a faulty design to the City of
Coppell and regardless of what Pate Brothers would have done i.e., install the line on grade or
install the line flat, as they did, HDR would have had to remove the line all the way back to
Freeway and enlarge it to a 15 inch sewer line.
HDR's position is that the City should direct Pate Brothers to remove the 10 inch line through
this 970 foot area and relay it as a 15 inch line on a different grade so that HDR can take
advantage of that and then only pay the difference of the cost between the 10 inch and the 15
inch. It should be noted that there are no bid items on this project for a 15 inch sewer line pipe
and the City would have to negotiate the price with Pate Brothers. When questioned, the Vice-
President of Pate Brothers stated that if he was required to remove and relay the 970 feet he
would do so as a 10 inch line on the grade proposed by HDR in the original design. Obviously,
by taking that approach, the entire 970 feet would have to be removed a second time and relayed
as a 15 inch sewer line.
It appears at this point because of HDR's reluctance to exceed a self imposed $100,000 limit and
the City of Coppell's inability to exceed $15,000 under State Purchasing Guidelines without
bidding, that this project is at an impasse. Therefore, the position taken by the City of Coppell
is to cease negotiations with the Firm of HDR, remove the 10 inch line that was erroneously
designed, relay a 15 inch line and then seek remedy from HDR in court to recoup the City's
cost.
Based on the above facts, staff recommends the approval of Change #1 to Pate Brothers in the
amount of $142,775.89 and will be available to answer any questions at the Council meeting.