Loading...
Rolling Oaks MC-CS080811 (4/5/2010) Michael Garza - Re: Cemetery Project SchedulePage 1 From: Brad Reid To:Michael Garza Date: 8/11/2008 4:57 PM Subject: Re: Cemetery Project Schedule Thanks Mike, this is perfect! >>> Michael Garza 8/11/2008 2:19 PM >>> Brad, Attached is the updated project schedule provided by The Fain Group. In a little more detail: The water line is installed, the storm drain is currently being installed. The piers have been poured for the decorative fence and they will begin installing the fence this week. The forms for the columbarium and the pavillion foundation are set and will be poured within a week. It looks like they are on track. If you have any questions please contact me at your convenience. thanks, mike