(4/7/2010) Michael Garza - Fwd: Rolling Oaks Cemetery: Section Pin Installation CostsPage 1
From: Tom Omick
To:Michael Garza
Date: 1/15/2009 5:10 PM
Subject: Fwd: Rolling Oaks Cemetery: Section Pin Installation Costs
Attachments:Response to PR 002.pdf
Mike,
We need to have a change order per these changes. Do we need to discuss this? It is basically the final process before
opening the cemetery for interments. How is the running?
Tom
>>> "Ken Baxter" <kbaxter@jstarchitects.com> 1/9/2009 8:26 AM >>>
Tom,
Attached is the contractor's pricing to provide section pins, surveying
and installing at the cemetery. Please have the appropriate parties
review and let us know how to direct the contractor for scheduling. If
the price is acceptable we will issue a Change Order for all parties to
execute and have on record.
Let us know if you have any questions.
Thanks,
Ken Baxter
Senior Project Manager
J. Stuart Todd, Inc.
Architecture/Interiors/Planning
2919 Welborn
Dallas, Texas 75219
214-522-4033
214-522-7988 fx.