April 20, 2010
L Lynn Kadleck, P.E.
Kadleck & Associates
555 Republic Dr., Suite 115
Plano, TX 75074
RE: Red Hawk
Plan Review Comments (3rd submittal)
The City of Coppell has reviewed the revised plans for the referenced addition and they will be
approved with the following comments addressed:
Grading Plan
1. Show the top of curb elevations on the grading plan.
2. The grading plan and the drainage area map do not match. Show the drainage easements on
the grading plan.
Paving Plan
3. Show PCR's elevations throughout the plans.
4. Stamped concrete only, no concrete pavers.
5. Revise details to match City of Coppell details.
6. How is sidewalk cutting through proposed screening wall?
7. Make sure you maintain the 2% cross slope for all crossing areas with barrier free ramps.
Drainage Plan
8. Drainage areas do not match grading plan.
9. Inlet 1 is a Sag inlet, how does it carry overflow?
10. How are you maintaining your crown through the intersection? We would feel more
comfortable with inlet 11 moved to lot 24. Show spot elevations through this intersection.
11. Show driveways adjacent to inlets on drainage area map.
12. Show that the alley can handle the additional runoff to the north.
Utility Plan
13. Make sure that you have correct separation for water and sewer.
14. Show the water and sewer as different line weights or styles.
15. Show all crossings on sewer profiles.
16. Make sure details refer to City of Coppell standard details.
The City of Coppell requires three sets of final construction plans for its use; your office should
submit as many additional sets for stamping as is necessary for construction operations. All
255 PARKWAY * P.O.BOX 9478 * COPPELL TX 75019 * TEL 972/462 0022 * FAX 972/304 3673
2
contractors and subcontractors onsite must have a copy of the plans approved by the City of Coppell
along with a copy of the City's standard construction details.
All fees must be paid prior to release of this project for construction. The City charges a 2%
inspection fee for all private construction outside the building's footprint. This includes dirt work,
paving, storm drains, water lines, sewer lines, drainage pipes, etc. that are private. For all
installations in the public right -of -way or easement, the City charges a 4% fee. A check for
inspection fees made to the City of Coppell should be submitted to this office along with the
Construction Development Permit Application and a copy of the Construction Site Notice. For your
convenience a spreadsheet is attached to the permit application for use in calculating the inspection
fees. A copy of the contract(s) should be attached for verification purposes.
If you have any questions, please contact me at your convenience.