MA1001-CS100602June 2, 2010
Adrian Bowman
Jim Bowman Construction Co., L.P.
2716 S. Rigsbee Dr.
Plano, TX 75074
RE: MA 10 -01 Denton Tap & Sandy Lake
Brick Paver Replacement
NOTICE TO PROCEED WITH CONSTRUCTION
Dear Mr. Bowman:
This letter will serve as your official notice to begin work on the referenced project. For
purposes of the contract, your calendar days will start June 7, 2010. Forty Five (45)
Calendar Days were bid on this project for completion of work. Therefore, we anticipate the
project being complete by July 22, 2010. For road and lane closure, reference the contract
documents.
If you have any questions or need any additional information please feel free to contact Rick
O'Dell, Construction Inspector at (972) 304 -7090.
Sincerely,
George Marshall, P.E.
Civil Engineer
Office 972/304 -3562
Fax 972/304 -7041
gmarshalI ,coppelltx.gov
cc: Kenneth Griffin, P.E., Director of Engineering/Public Works
Rick O'Dell, Construction Inspector