MA1001-CS100511Jim Bowman Construction Co., L.P.
1111 Summit Avenue, Suite 1
Plano, TX 75074
(972) 423 -1313
To: Mr. George Marshall, P.E.
City of Coppell
255 E. Parkway Blvd.
Coppell, Tx 75019
LETTER OF TRANSMITTAL
Date: 05/11/10 Job No: 876
Regarding: Pre -Con Submittals
Denton Tap & Sandy Lake Road
WE ARE SENDING YOU: E] Attached ❑ Under separate cover via
❑ Shop Drawings ❑ Prints ❑ Plans ❑ Samples
❑ Copy of Letter ❑ Change Order ❑
the following items:
❑ Specifications
COPIES
DATE
NO.
DESCRIPTION
1
5/11/10
Emergency Contacts /Subcontractors
1
5/11/10
Proposed Schedule
3
5/11/10
Concrete Mix Designs
1
5/11/10
Contractor Qualifications
I
LE
THESE ARE SUBMITTED (as checked below)
E For approval
El For your use
EZ As requested
❑ For review and comments
❑ FOR BIDS DUE
REMARKS
❑ Resubmit
copies for approval
❑ Submit
copies for distribution
❑ Return
corrected prints
2007 ❑ PRINTS RETURNED AFTER LOAN TO US
Let me know if you need additional information
❑ Approved as submitted
❑ Approved as noted
❑ Returned for corrections
COPY TO Project File SIGNED ; '
JIM BOWMAN CONSTRUCTION COMPANY, INC.
2716 S. Rigsbee Dr. ■ Plano, Texas 75074 ■ (972) 423 -1313
May 11, 2010
Mr. George Marshall, P.E.
City of Coppell
255 E. Parkway Blvd.
Coppell, TX 75019
Re: JBCC Project #876 — Denton Tap & Sandy Lake Road
We offer the following list of personnel for emergency contact purposes:
Name Title Cell Phone Home
Adrian Bowman Assistant GM (214) 535 -6588 (972) 208 -6018
Vicente Murillo Paving Superintendent (214) 535 -2804 (972) 487 -9362
Lee Halencak Director of Operations (972) 339 -8511 (214) 693 -8250
Jim Bowman General Manager (214) 926 -7398 (972) 509 -1599
Subcontractors
Metroplex Pavement Markings
North Texas Bomanite
Please call if you have any questions.
Sincerely,
Lee M. Halencak, P.E.
Director of Operations
s a ` Ci tr_Rr1F1on (3 it.( ems
-- Sitlito
/ 60 r'( / - 4 F'7z fc“( _S.S____‘_z
0 _r c / . c)7 .F,)4 7‘
M,v 1,t4 6467.6 Z if 97 /Z3 - 1513
,t ;r
L A, liulenc:4K
1 0 ot, -- 8 r ow er N. i c.Xks 3oma a ►-} e 17 2. - 9 N- 7 4 63
II) EEL) Dfit/j__ CO PPLZ . V/2-36?-368 (-
/6 , /16:-.,-)' c', i(
1 2 zA- G e‘r2,,./q ` - z 3, 7
1
i
Denton Tap & Sandy Lake Brick Paver Replacement
Construction Schedule
JBCC Project No. 876
Jim Bowman Construction Company, LP
Tue 5/11/10
ID Task Name
Duration
Start
Finish Predecessors
Jun 6 10 Jun 13 10 Jun 20 '10 Jun 27 10 Ju 4'10
1 Denton Tap & Sandy Lake Brick Paver Replacement
30 days
Mon 6/7/10
Tue 7/6/10
S M,T Wi TF SS:MiT YV TF S'S IMT W;TF ?S,SiM -T W!TiF!S,S MT W.
2 Phase I
14 days
Mon 6 /7/10
Sun 6/20/10
3 Barricades / Detour Setup
1 day
Mon 6/7/10
Mon 6/7/10
4 Sawing
0.5 days
Tue 6/8/10
Tue 6/8/10 3
5 Pavement / Paver Removals
1.5 days
Tue 6/8/10
Wed 6/9/10 4
6 12" RC Pavement
5 days
Thu 6/10/10
Mon 6/14/10 5
7 12" Stamped RC Pavement
5 days
Tue 6/15/10
Sat 6/19/10 6
8 BFRs & Sidewalks
1 day
Sun 6/20/10
Sun 6/20/10 7
9 Phase II
13 days
Mon 6121/10
Sat 7/3/10 2
10 Barricades / Traffic Switch
1 day
Mon 6/21/10
Mon 6/21/10
11 Sawing
0.5 days
Tue 6/22/10
Tue 6/22/10 10
12 Pavement / Paver Removals
1.5 days
Tue 6/22/10
Wed 6/23/10 11
13 12" RC Pavement
5 days
Thu 6/24/10
Mon 6/28/10 12
14 12" Stamped RC Pavement
5 days
Tue 6/29/10
Sat 7/3/10 13
15 r Pavement Markings
2 days
Sun 7/4/10
Mon 7/5/10 9
16 Clean -up / Punchlist
I
1 day
Tue 7/6/10
Tue 7/6/10 15