MA1001-CS100609Denton Tap & Sandy Lake Brick Paver Replacement JBCC Project No 876
Construction Schedule
Wed 6/9/10
Jim Bowman Construction Company, LP
ID
Task Name
Duration
Start
Finish
Jun
—
- -._
S S M
1
;Denton Tap & Sandy Lake Brick Paver Replacement
28 days
Mon 6/7/10
Sun 7/4/10
C
2
Phase I - Inside Lanes
13 days
Mon 6/7/10
Sat 6/19/10
3
Barricades / Detour Setup
1 day
Mon 6/7/10
Mon 6/7/10
4
Sawing
0.5 days
Tue 6/8/10
Tue 6/8/10
5
Pavement / Paver Removals
1.5 days
Tue 6/8/10
Wed 6/9/10
6
12" RC Pavement
5 days
Thu 6/10/10
Mon 6/14/10
7
12" Stamped RC Pavement
5 days
Tue 6/15/10
Sat 6/19/10
8
Phase 11 - Outside Lanes
13 days
Sun 6/20/10
Fri 7/2/10
9
Barricades / Traffic Switch
1 day
Sun 6/20/10
Sun 6/20/10.
_ 10
Sawing
0.5 days
Mon 6/21/10
Mon 6/21/10;
11
Pavement / Paver Removals
1.5 days
Mon 6/21/10
Tue 6/22/101
12
12" RC Pavement
5 days
Wed 6/23/10
Sun 6/27/10,
13
12" Stamped RC Pavement
5 days
Mon 6/28/10
Fri 7/2/10.
14
BFRs & Sidewalks
3 days
Mon 6/28/10
Wed 6/30/10',
15
Pavement Markings
1 day
Sat 7/3/10
Sat 7/3/10';
16
Clean -up / Punchlist
1 day
Sun 7/4/10
Sun 7/4/101
Jun 13, '10 Jun 20, '10 Jun 27, '10 Jul 4
SIM1T iT,F,S,S M T W T;F,S.S M T W T F S S M