Tennis Ctr Exp-CS100524KKnley -Hom
and Associates, Inc.
Coppell Tennis Center Improvements
Denton, Texas
PRE- CONSTRUCTION MEETING AGENDA
Date: Monday, May 24, 2010
2:00 PM
Attending: City of Coppell Representatives
Schmoldt Construction Representatives
Kimley -Horn Representatives
Subcontractors
Introduction of Parties and Responsibilities
A. Owner (City of Coppell, Texas)
B. Contractor ( Schmoldt Construction)
C. Consultants (Kimley -Horn)
D. Signed Attendance Roster (See attached sign -in sheet)
II. Finalization of Contracts
A. Distribution of Signed Copies of Contracts
City will distribute signed contracts at meeting. (Verify)
B. Written Notice to Proceed
City will send a written Notice to Proceed Letter with contracts (Verify)
C. Subcontractor List
Contractor needs to submit a complete Sub Contractor's List within
twenty (20) calendar days of receipt of signed contract.
I11. Processing of Decisions
A. Field Orders / Clarifications
Refer to Project Manual, Division 1— Section 01020.
B. Change Orders
Refer to Project Manual, Division 1 — Section 01020 (No work requiring
additional compensation will be performed without a fully executed
Change Order)
C. Communication
1. Owner to Consultant
Ester Moreno will be Primary Point of Contact with City.
2. Consultant to Contractor
John Fielder will be Primary Point of Contact with Consultants.
3. Contractor to Consultant/Owner
will be Primary Point of Contact with Contractor.
4. Sub - Contractor to Contractor
Sub Contractors shall forward all requests for information,
submittals, etc. through Contractor to the Consultants
IV. Payment Processing
A. Schedule of Values
Contractor needs to submit a schedule of values for review and approval
by the Consultant (AIA Form G703) Refer to Project Manual, Division 1
- Section 01020 (Two Days from Receipt of Contract.)
B. Project Meetings
Refer to Project Manual, Division 1 - Section 01039 (Kimley -Horn will
attend regularly scheduled monthly meetings — six total.) City will attend
weekly meetings. Contractor shall hold weekly subcontractor meetings
prior to regular scheduled meetings.
C. Owner's Payment Procedures Discuss dates to submit payments
The City processes checks monthly (Verify). Contractor to submit
monthly pay applications ten days prior to due date for review by
Kimley -Horn and Owner (ideally at monthly meetings.) Refer to Project
Manual, Division 1— Section 1020.
D. Liquidated Damages
Liquidated damages will be assessed at $250 per day beyond the project
completion date.
V. Scheduling (Refer to Division 1 — Section 0 13 00, Item 1.4)
A. Construction Schedule
1. Phasing of Work
2. Schedule Submittal
Contractor to submit construction schedule for review and approval
by Kimley -Horn w/n twenty (20) calendar days of receipt of contract.
B. Mobilization
1. Job Shack and Staging Area
Coordinate Location with City.
2. Contractor's Access to Site
Refer to Project Manual.
3. Permits and Fees
Contractor needs to File NOI or Construction Letter and Fees— All
Other City Permit Fees are Waived (Verify.)
4. Inspections
Schmoldt Construction to Coordinate City Engineering and Building
Inspections with City.
VI. Submittal Process
A. List of Submittals
Contractor to Provide List of Submittals within twenty (20) calendar days
of receipt of signed contract to Kimlev -Horn for Approval — See Proiect
Manual, Division 1 - Section 01300.
Need all submittals within first 30 days if possible.
B. Substitutions
Refer to Project Manual, Division 1— Section 01630.
C. Mix Designs and Test Reports
See Project Manual, Division 1 - Section 01410
Owner will contract with PSI (Professional Service Industries, Inc.) for
Testing Services
Contractor will call for tests as required.
D. Shop Drawings /Samples
See Proiect Manual, Division 1 - Section 01340. Shop drawings to be
submitted within thirty (30) days prior to the contractor /supplier's
needed date and samples involving colors and selections to be submitted
within first thirty (30) days so a color schedule and board can be
Prepared. Long lead items (waterslides, pool filters and pumps, water
play features, etc. should be submitted within the first (30) days.
VI. Record Drawings / Project Close -out
Refer to Project Manual, Division 1— Section 01700
VII. Miscellaneous
A. Safety
Refer to Project Manual, Division 1— Section 01500
B. Condition of Site and Staging Area
Refer to Project Manual, Division 1— Section 01500
C. Existing Utilities, Existing Trees, Tree Protection
Refer to Project Manual, Division 1— Section 01500
D. Clean Up
Refer to Project Manual, Division 1— Section 01500
E. Topsoil Storage Area
To be Approved by Owner
F. Date of Next Meeting
VIII. Comments /Questions /Action Items:
A. If contractors need to work on Saturday, they must notify the Owner by
noon on Wednesday. Saturday hours are between 9 a.m. - 4 p.m.
Working on Sunday is not allowed. (Verify w/ Owner.)
Note: These meeting notes were prepared by Kimley -Horn and Associates, Inc. Should
any corrections or modifications be required to these notes, corrections will be noted in
on the subsequent meeting notes.