SS9402C-CN 960719PROJECT:
CONTRACTOR:
OWNER:
CHANGE ORDER NO.:
CITY OF COPPELL
CHANGE OR EXTRA WORK ORDER
Bethel Road Sanitary Sewer Project / SS 92-04C
Pate Brothers Construction, Inc.
Item
ADD: 1
2
City of Coppell
1
DATE:
CHANGE OR EXTRA WORK TO BE DONE
Description Quantity Unit
July 19, 1996
Unit Total
Price
Extra depth for S/S 772 LF 2.95 2,277.40
installation
Extended Traffic 59 Days 93.75 5,531.25
Control
Total Revision to Contract Amount $7,808.65
Previous contract mount
Net increase in contract amount
Revised contract amount
Net increase in contract time of completion
Revised Contract time of completion
$ 345,454.69
$7,808.65
$ 353,263.34
-0- Days
180 Days
The contractor hereby accepts this Contract adjustment as a final and complete adjuslment in full
accord and satisfaction of all past and future liability originating under any clause in the Contract
by reason of this revision to the Contract.
Recommende~l~by the City Engineer:
Ag~ed to by the Contractor:
wner:
Date: I'
Date: