SS9402C-CS 960329 (2)CONSTRUCTION, INC.
March 29, 1996
04-03-96A10:41 RCVD
City of Coppell
255 Parkway
Coppell, Texas 75019
RE: Bethel ~ Road Sewer Project
ATTN: Mr. Ken Griffin
Gentlemen:
As of this date, our portion of work on the above named project is
basically complete. We need to finish some clean-up items'.
As for the connection to the wet well, I assume it is under
discussion and you will let me know of your decision.
Also, there are a couple of unfinished items that need to be
addressed by the Cityl We will need answers on the following
items:
1) Sewer depth over 15'.
2) Barricades furnished to the county for their work to be
completed. The county said they would be no later than one
week behind us to complete their work. We have been gone from
this site for 2 weeks and they have not completed their
portion of work. We will be looking to be reimbursed for the
extra delay time on the traffic control.
3) The connection to Postal Service building (under discussion at
this time).
4) Re-mobile to complete this connection if needed.
Please discuss these items and let me know at your earliest
convenience.
Sincerely,
D~o~A~E BROTHERS CONSTRUCTION,
Vice President
INC.