ST0301A-CS100401 (2)2010) Keith Marvin - Bethel Rd II Page 1 From: "Martin Elliott" <MElliott @aggengr.com> To: "Keith Marvin" <kmarvin @coppelltx.gov> Date: 4/1/2010 5:26 PM Subject: Bethel Rd II Attachments: P 10- 0327C. pdf Keith, Please find attached an estimate for construction testing on the above project. I visited with Larry in regards to this proposal and feel like we should have a good number. If you feel that we are a little light, can put in a "contingency" for extra testing at the city's request. If you have any questions let me know. Thanks, Marty Martin J. Elliott, P. E., LEED AP Principal Alliance Geotechnical Group Texas Registered Engineering Firm F -1970 3228 Halifax Street Suite A Dallas, TX 75247 Phone: 972 - 444 -8889 Fax: 972 - 444 -8893 Direct: 972 - 331 -8801 www.aggengr.com <http: / /www.aggengr.com> "Employee Owned- Client Driven" META- April 1, 2010 Mr. Keith Marvin, P.E. City of Coppell 255 E. Boulevard Coppell, Texas 75019 Re: Bethel Road II Coppell, Texas Engineering Inspection & Testing Services AGG Proposal No: P10- 0327CR Dear Mr. Marvin: • GEOTECHNICAL ENGINEERING • ENVIRONMENTAL CONSULTING • CONSTRUCTION MATERIALS ENGINEERING AND TESTING Phn: (972) 304 -3681 Fax: (972) 304 -3570 Alliance Geotechnical Group (AGG) is pleased to confirm our firm's interest in providing materials inspection and testing services for the proposed Bethel Road project noted above. A schedule of unit fees for this project is attached. After reviewing our fee schedule if you have any questions, please contact the undersigned at (972) 444 -8889. If acceptable, please sign below and fax back to our office as our Authorization to Proceed. We look forward to the opportunity of working with you on this project. Respectfully submitted, ALLIANCE GEOTECHNICAL GROUP Roe P. Nance, C.E.T. Sr. Project Manager Approved by: Signature Date: MEMBER 3228 Halifax Street • Suite A • Dallas, Texas 75247 � Tel: 972- 444 -8889 • Fax: 972 - 444 -8893 • www.aggengr.com AB 1l; SCHEDULE OF FEES FOR CONSTRUCTION MATERIALS ENGINEERING & TESTING BETHEL ROAD II COPPELL, TEXAS 3 AGG PROPOSAL NO.: P10- 0327CR DESCRIPTION OF SERVICES QUANTITY $450.00 UNIT FEE UNIT FEE A. MASS GRADING, LIME AND WALL BACKFILL TESTIN & INSPECTION each $150.00 • Sieve Analysis for Embedment 2 • Moisture /Density Relationship of Soils (ASTM D -698) 8 @ $150.00 each $1,200.00 • Atterberg Limits 13 @ $50.00 each $650.00 • Lime Series ( 5 point PI method) 4 @ $225.00 each $900.00 • Cement Series ( as needed) $37.00 @ $375.00 each $0.00 • Sulfate Test 4 @ $90.00 each $360.00 • Paving Subgrade Density Test ( 1 per 300 If/ lift) 14 @ $13.00 each $182.00 • Sidewalk Density Tests ( 1 per 300 If) 28 @ $13.00 each $364.00 • Lime Gradation Test (1 per 300 If) 14 @ $13.00 each $182.00 • Lime Depth Verification (1 per 300 If) 14 @ $13.00 each $182.00 • Lime Subgrade In -Place Density Test (1 per 300 If) 14 @ $13.00 each $182.00 • Retaining Wall / Abutment Backfill Density Test (1 per lift) 60 @ $13.00 each $780.00 • Sr. Engineering Tech to perform testing 148 @ $37.00 hour $5,476.00 • Project Manager 6 @ $75.00 hour $450.00 • Geotechnical Project Manager( as needed) @ $90.00 hour $0.00 • Sr. Geotechnical Engineer ( as needed) @ $110.00 hour $0.00 • Vehicle Charge 40 @ $35.00 trip $1,400.00 Sub -Total $12,308.00 B. UTILITY BACKFILL TESTING & INSPECTION • Moisture /Density Relationship of Soils (ASTM D -698) 3 @ $150.00 each $450.00 • Atterberg Limits 3 @ $50.00 each $150.00 • Sieve Analysis for Embedment 2 @ $35.00 each $70.00 • In -Place Density Test* (ASTM D2922) (1 fdt per 150 If) 60 @ $13.00 each $780.00 • Concrete Test Cylinders (4 cyls per set) inlets,manholes 20 @ $14.00 each $280.00 • Sr. Engineering Tech to perform testing 72 @ $37.00 hour $2,664.00 • Project Manager 4 @ $75.00 hour $300.00 • Vehicle Charge 24 @ $35.00 trip $840.00 • Vehicle Charge 89 @ $35.00 Sub -Total $5,534.00 C. CONCRETE & REINFORCING TESTING & INSPECTION • Concrete Inspection & Testing (regular time) 328 @ $37.00 hour $12,136.00 • Concrete Cylinder Test -(4 cyls per 100 cyd ) Paving 132 @ $14.00 each $1,848.00 • Concrete Cylinder Test -(4 cyls per 100 cyd ) - Sidewalk 32 @ $14.00 each $448.00 • Concrete Cylinder Test -(4 cyls per 100 cyd ) - Driveways 32 @ $14.00 each $448.00 • Concrete Cylinder Test -(4 cyls per 100 cyd ) - Bridge 132 @ $14.00 each $1,848.00 • Concrete Beam Test -(4 bms / 100 cyd) - Bridge deck 8 @ $24.00 each $192.00 • Concrete Core Depth Checks ( 2" dia core / 300 If) 14 @ $40.00 each $560.00 • Project Manager 8 @ $75.00 hour $600.00 • Vehicle Charge 89 @ $35.00 trip $3,115.00 Sub -Total $21,195.00 P10- 0327CR SCHEDULE OF FEES FOR CONSTRUCTION MATERIALS ENGINEERING & TESTING BETHEL ROAD II COPPELL, TEXAS AGG PROPOSAL NO.: P10- 0327CR DESCRIPTION OF SERVICES QUANTITY UNIT FEE UNIT FEE D. DRILLED PIER INSPECTION & TESTING • Drilled Pier Inspection & Testing (regular time) 52 @ $37.00 hour $1,924.00 • Concrete Cylinder Test -(4 cyls per set) - Piers 24 @ $14.00 each $336.00 • Project Manager 2 @ $75.00 hour $150.00 • Geotechnical Project Manager 6 @ $88.00 hour $528.00 • Vehicle Charge 9 @ $35.00 trip $315.00 Sub -Total $3,253.00 ESTIMATED TOTAL $42,290.00 NOTES: 1. Overtime rates of 1.5 times the regular hourly rate will be charged for hours worked over eight (8) hours per day Monday thru Friday or any time before 7:00 a.m. or after 5:00 p.m. Service performed on Saturdays and Sundays will be billed at 1.5 times the regular hourly rate. Services performed on recognized holidays will be billed at 2.0 times the regular hourly rate. ( WILL BE BILLED TO CONTRACTOR) 2. All laboratory test fees are F.O.B. our laboratory; additional charge for sample pickup may apply. 3. Any additional tests will be billed on a hourly rate and charged at the applicable rate, portal -to- portal. 4. Additional test not specified in this proposal will be quoted upon request. 5. This proposal does not include any technician stand -by, non - readiness charges, and /or trips or re -tests of the previous failing tests. 6. The above unit rates are based on the following estimated schedule: * Drilled pier inspection- 6 days Bridge bents- 4 placements estimated Bridge Abutments- 4 placements estimated Bridge Columns- 4 placements estimated Bridge Approach slabs- 4 placements estimated * Bridge rails- 2 placements estimated Bridge sidewalks- 2 placements estimated Concrete paving- 10 placements estimated Barrier free ramps- 4 placements estimated Driveways- 4 placemets estimated Sidewalks- 4 placemets estimated Retaining walls- 10 placements estimated Lime subgrade- 6 days of mixing estimated Mass grading -8 days estimated Retaining wall backfill- 16 days estimated P10- 0327CR