ST0301A-CS100401 (2)2010) Keith Marvin - Bethel Rd II Page 1
From:
"Martin Elliott" <MElliott @aggengr.com>
To:
"Keith Marvin" <kmarvin @coppelltx.gov>
Date:
4/1/2010 5:26 PM
Subject:
Bethel Rd II
Attachments:
P 10- 0327C. pdf
Keith,
Please find attached an estimate for construction testing on the above
project. I visited with Larry in regards to this proposal and feel like
we should have a good number. If you feel that we are a little light,
can put in a "contingency" for extra testing at the city's request.
If you have any questions let me know.
Thanks,
Marty
Martin J. Elliott, P. E., LEED AP
Principal
Alliance Geotechnical Group
Texas Registered Engineering Firm F -1970
3228 Halifax Street
Suite A
Dallas, TX 75247
Phone: 972 - 444 -8889
Fax: 972 - 444 -8893
Direct: 972 - 331 -8801
www.aggengr.com <http: / /www.aggengr.com>
"Employee Owned- Client Driven"
META-
April 1, 2010
Mr. Keith Marvin, P.E.
City of Coppell
255 E. Boulevard
Coppell, Texas 75019
Re: Bethel Road II
Coppell, Texas
Engineering Inspection & Testing Services
AGG Proposal No: P10- 0327CR
Dear Mr. Marvin:
• GEOTECHNICAL ENGINEERING
• ENVIRONMENTAL CONSULTING
• CONSTRUCTION MATERIALS ENGINEERING AND TESTING
Phn: (972) 304 -3681
Fax: (972) 304 -3570
Alliance Geotechnical Group (AGG) is pleased to confirm our firm's interest in providing
materials inspection and testing services for the proposed Bethel Road project noted above. A
schedule of unit fees for this project is attached.
After reviewing our fee schedule if you have any questions, please contact the undersigned at
(972) 444 -8889. If acceptable, please sign below and fax back to our office as our Authorization
to Proceed. We look forward to the opportunity of working with you on this project.
Respectfully submitted,
ALLIANCE GEOTECHNICAL GROUP
Roe P. Nance, C.E.T.
Sr. Project Manager
Approved by:
Signature
Date:
MEMBER 3228 Halifax Street • Suite A • Dallas, Texas 75247 �
Tel: 972- 444 -8889 • Fax: 972 - 444 -8893 • www.aggengr.com AB 1l;
SCHEDULE OF FEES
FOR
CONSTRUCTION MATERIALS ENGINEERING & TESTING
BETHEL ROAD II COPPELL, TEXAS
3
AGG PROPOSAL NO.: P10- 0327CR
DESCRIPTION OF SERVICES
QUANTITY
$450.00
UNIT FEE
UNIT
FEE
A. MASS GRADING, LIME AND WALL BACKFILL TESTIN & INSPECTION
each
$150.00
• Sieve Analysis for Embedment
2
• Moisture /Density Relationship of Soils (ASTM D -698)
8
@
$150.00
each
$1,200.00
• Atterberg Limits
13
@
$50.00
each
$650.00
• Lime Series ( 5 point PI method)
4
@
$225.00
each
$900.00
• Cement Series ( as needed)
$37.00
@
$375.00
each
$0.00
• Sulfate Test
4
@
$90.00
each
$360.00
• Paving Subgrade Density Test ( 1 per 300 If/ lift)
14
@
$13.00
each
$182.00
• Sidewalk Density Tests ( 1 per 300 If)
28
@
$13.00
each
$364.00
• Lime Gradation Test (1 per 300 If)
14
@
$13.00
each
$182.00
• Lime Depth Verification (1 per 300 If)
14
@
$13.00
each
$182.00
• Lime Subgrade In -Place Density Test (1 per 300 If)
14
@
$13.00
each
$182.00
• Retaining Wall / Abutment Backfill Density Test (1 per lift)
60
@
$13.00
each
$780.00
• Sr. Engineering Tech to perform testing
148
@
$37.00
hour
$5,476.00
• Project Manager
6
@
$75.00
hour
$450.00
• Geotechnical Project Manager( as needed)
@
$90.00
hour
$0.00
• Sr. Geotechnical Engineer ( as needed)
@
$110.00
hour
$0.00
• Vehicle Charge
40
@
$35.00
trip
$1,400.00
Sub -Total
$12,308.00
B. UTILITY BACKFILL TESTING & INSPECTION
• Moisture /Density Relationship of Soils (ASTM D -698)
3
@
$150.00
each
$450.00
• Atterberg Limits
3
@
$50.00
each
$150.00
• Sieve Analysis for Embedment
2
@
$35.00
each
$70.00
• In -Place Density Test* (ASTM D2922) (1 fdt per 150 If)
60
@
$13.00
each
$780.00
• Concrete Test Cylinders (4 cyls per set) inlets,manholes
20
@
$14.00
each
$280.00
• Sr. Engineering Tech to perform testing
72
@
$37.00
hour
$2,664.00
• Project Manager
4
@
$75.00
hour
$300.00
• Vehicle Charge
24
@
$35.00
trip
$840.00
• Vehicle Charge
89
@
$35.00
Sub -Total
$5,534.00
C. CONCRETE & REINFORCING TESTING & INSPECTION
• Concrete Inspection & Testing (regular time)
328
@
$37.00
hour
$12,136.00
• Concrete Cylinder Test -(4 cyls per 100 cyd ) Paving
132
@
$14.00
each
$1,848.00
• Concrete Cylinder Test -(4 cyls per 100 cyd ) - Sidewalk
32
@
$14.00
each
$448.00
• Concrete Cylinder Test -(4 cyls per 100 cyd ) - Driveways
32
@
$14.00
each
$448.00
• Concrete Cylinder Test -(4 cyls per 100 cyd ) - Bridge
132
@
$14.00
each
$1,848.00
• Concrete Beam Test -(4 bms / 100 cyd) - Bridge deck
8
@
$24.00
each
$192.00
• Concrete Core Depth Checks ( 2" dia core / 300 If)
14
@
$40.00
each
$560.00
• Project Manager
8
@
$75.00
hour
$600.00
• Vehicle Charge
89
@
$35.00
trip
$3,115.00
Sub -Total $21,195.00
P10- 0327CR
SCHEDULE OF FEES
FOR
CONSTRUCTION MATERIALS ENGINEERING & TESTING
BETHEL ROAD II COPPELL, TEXAS
AGG PROPOSAL NO.: P10- 0327CR
DESCRIPTION OF SERVICES
QUANTITY
UNIT FEE
UNIT
FEE
D. DRILLED PIER INSPECTION & TESTING
• Drilled Pier Inspection & Testing (regular time)
52
@
$37.00
hour
$1,924.00
• Concrete Cylinder Test -(4 cyls per set) - Piers
24
@
$14.00
each
$336.00
• Project Manager
2
@
$75.00
hour
$150.00
• Geotechnical Project Manager
6
@
$88.00
hour
$528.00
• Vehicle Charge
9
@
$35.00
trip
$315.00
Sub -Total
$3,253.00
ESTIMATED TOTAL
$42,290.00
NOTES:
1. Overtime rates of 1.5 times the regular hourly rate will be charged for hours worked over eight (8) hours
per day Monday thru Friday or any time before 7:00 a.m. or after 5:00 p.m. Service performed on Saturdays
and Sundays will be billed at 1.5 times the regular hourly rate. Services performed on recognized holidays
will be billed at 2.0 times the regular hourly rate. ( WILL BE BILLED TO CONTRACTOR)
2. All laboratory test fees are F.O.B. our laboratory; additional charge for sample pickup may apply.
3. Any additional tests will be billed on a hourly rate and charged at the applicable rate, portal -to- portal.
4. Additional test not specified in this proposal will be quoted upon request.
5. This proposal does not include any technician stand -by, non - readiness charges, and /or trips or re -tests of the
previous failing tests.
6. The above unit rates are based on the following estimated schedule:
* Drilled pier inspection- 6 days
Bridge bents- 4 placements estimated
Bridge Abutments- 4 placements estimated
Bridge Columns- 4 placements estimated
Bridge Approach slabs- 4 placements estimated
* Bridge rails- 2 placements estimated
Bridge sidewalks- 2 placements estimated
Concrete paving- 10 placements estimated
Barrier free ramps- 4 placements estimated
Driveways- 4 placemets estimated
Sidewalks- 4 placemets estimated
Retaining walls- 10 placements estimated
Lime subgrade- 6 days of mixing estimated
Mass grading -8 days estimated
Retaining wall backfill- 16 days estimated
P10- 0327CR