ST0301A-CS100528
(8/13/2010) Keith Marvin - RE: Bethel Road IIPage 1
From:
"Marty Murphy" <Martym@JRJPaving.com>
To:
"Keith Marvin" <kmarvin@coppelltx.gov>
Date:
5/28/2010 1:13 PM
Subject:
RE: Bethel Road II
thanks
-----Original Message-----
From: Keith Marvin [mailto:kmarvin@coppelltx.gov]
Sent: Friday, May 28, 2010 1:08 PM
To: Marty Murphy
Cc: Caleb Thornhill
Subject: Re: Bethel Road II
I've left a message for Oncor. I'm available at 1:30 on Tuesday. I'll
let you know if they can make it.
Keith
Keith Marvin, P.E.
Project Engineer
(972) 304-3681
>>> "Marty Murphy" <Martym@JRJPaving.com> 5/28/2010 12:34 PM >>>
Here is the schedule we are looking at for the bridge to help facilitate
the coordination meeting for power shut down by Oncor;
6/14 - shut down road, demo bridge
6/21 - channel excavation, drill piers (need power shut down 6/21-6/25)
7/5-7/26 - complete channel excavation, pour abutments and caps and rip
rap
8/2 - set beams and panels ( need power shut down 8/2-8/6)
8/9-9/7 - complete bridge and open to two lanes of traffic
Please review and see if we can set up a meeting for next Tuesday in the
afternoon if possible to discuss in the field with Oncor.
Thanks for your help.
Marty