Keith Marvin - Bethel Rd - Additional Time
From: "Dean Dumke" <deand@JRJPaving.com>
To: "Keith Marvin" <kmarvin@coppelltx.gov>
Date: 6/24/2010 11:32 AM
Subject: Bethel Rd - Additional Time
Keith,
Due to the need for additional information and days taken to ensure we had the correct information for the
th
grades in the bridge slopes were correct. I would like to request 3 additional days added to the September 7
finish date.
Dean Dumke
Sr Project Manager
469-223-7879
JRJ PAVING, L. P.